What it is
Pauses, Bans and Local Fights
A moratorium halts approvals for new data centers for a set time or until new rules are written. In 2026 they spread from a few counties to whole states, alongside zoning bans, lawsuits and the withdrawal of tax breaks.
- Scale: Data Center Watch counted about $130B of US projects blocked or delayed in the first quarter of 2026 alone, and 843 local opposition groups by September. Its method is not public, and a delay is not a cancellation.
- States: New York paused permits for sites of 50 MW and up, Texas paused interconnection and state permits pending an audit, Maine passed a statewide moratorium that was vetoed, Vermont's governor vetoed a bill setting data center siting and cost rules, and at least 14 states filed moratorium bills. Ohio, Illinois and Arizona froze data center tax incentives.
- Opponents' case: power bills and grid strain, water use in drought, noise, lost farmland, rising home prices, tax breaks and few permanent jobs. A Brookings study found a county's first large data center adds roughly 100-200 jobs.
- Builders' case: data centers pay large tax bills; in Loudoun County, Virginia, they provide 38% of the county's general fund. Developers increasingly offer closed-loop or air cooling, their own generation and community funds, and argue that much opposition rests on outdated information about water and power.
- Where projects go: some rejected projects move rather than end. Tucson's Project Blue was rejected by the city and approved by the surrounding county with air cooling and community funds.
- Abroad: Ireland, the Netherlands, Singapore and Malaysia limited new sites over grid capacity, land and water. Little local opposition in China appears in public reporting; its limits come from central planning, which steers new sites to western hubs and caps their energy use.
Flagship
Texas: The Largest Market Pauses
- Queue: ERCOT's interconnection queue held more than 474 GW of requests from about 1,800 projects by August 2026, about 90% of them data centers.
- Local: in 2026 Hill County passed a moratorium in May and lifted it within weeks after a federal lawsuit, San Marcos banned data centers in every zoning district, and Hays County suspended approvals for high-water-use projects.
- Audit: on 3 August 2026 Gov. Greg Abbott ordered the PUCT and ERCOT to audit every queued data center; none may advance until the audit is done. The audit requires disclosure of tax breaks, power and water use, cooling, community impacts and ownership. Separately, the PUCT's proposed SB 6 large-load rule would require site control and $50,000 per MW of upfront financial security.
- Pause: on 21 September Abbott ordered the TCEQ to pause all pending and new data center permits until the audits finish. ERCOT expects to file its audit reports by 10 December 2026.
- Gaps: self-powered projects and areas outside ERCOT are not clearly covered.
- More: the Texas moratorium explained at AustinIO.
Actions
Moratoriums, Bans and Limits
| Action | What | Date |
|---|---|---|
| Texas statewide pause | Interconnection audit of every queued data center; TCEQ permits paused | August-September 2026 |
| San Marcos, Texas | Bans data centers in every zoning district, the first Texas city to do so | June 2026 |
| Hays County, Texas | Suspends discretionary approvals for high-water-use projects; water review board | June 2026 |
| Hill County, Texas | Moratorium of up to one year, lifted within weeks after a federal lawsuit | May-June 2026 |
| New York, EO 62 | Pauses state environmental permits for data centers of 50 MW and up | July 2026 |
| Maine | Statewide moratorium bill passed and vetoed | April 2026 |
| Vermont | Data center standards bill (H.727) vetoed | May 2026 |
| Prince William Digital Gateway, Virginia | About 2,100 acres beside Manassas battlefield; rezoning voided, appeals dropped | July 2026 |
| Microsoft Caledonia, Wisconsin | 244-acre site dropped "based on the community feedback we heard" | October 2025 |
| Project Blue, Tucson | Rejected by the city; approved by Pima County with closed-loop air cooling and $15M of community funds | December 2025 |
| Ohio, Illinois, Arizona | State data center tax incentives frozen or paused | 2026 |
| Ireland, Dublin | De facto pause since 2022; new sites must bring their own generation or storage | December 2025 |
| Netherlands | Hyperscale permits limited to two sites; Meta's 200 MW Zeewolde campus cancelled | 2022 |
| Singapore | 2019-2022 moratorium; 200 MW awarded to four operators in the second allocation round | August 2026 |
| Malaysia | Johor stops approving low-tier water-heavy sites; nationwide freeze on new non-AI data centers | 2025-2026 |
| China | Central limits: PUE caps of 1.25 at eastern hubs and 1.2 at western hubs, sites steered west, local small compute projects banned | 2022-2025 |
Record
Dataset Record
- Dataset
- Data center moratoriums, bans, local opposition and national limits
- Sources
- Office of the Texas Governor, ERCOT, DLA Piper, Foley, Texas Tribune, KUT, Route Fifty, Jones Day, ION Analytics, Virginia Lawyers Weekly, DatacenterDynamics, AZ Luminaria, Data Center Watch, Brookings, Loudoun Now, CRU, CSO Ireland, Singapore EDB, Malay Mail, Xinhua, Reuters