Google's flexible load
Google Writes Curtailment Into Its Utility Contracts
- Scale: on March 19, 2026, Google said it has 1 GW of demand response written into long-term contracts with US utilities: Indiana Michigan Power and TVA first (August 2025), then Entergy Arkansas, Minnesota Power and DTE Energy.
- How it works: when a utility signals grid stress, Google cuts or shifts part of its machine learning work for certain hours or times of year; training jobs can pause where live services cannot.
- Why utilities agree: Google says flexible load lets new data centers connect sooner than firm load would.
- Not disclosed: curtailment hours, sites and MW per utility.
- Background: a 2024 pilot with a Nebraska utility cut machine learning demand in three grid events; earlier, Google shifted YouTube video processing in Belgium and Taiwan.
See Google Project Tembo.
Grid headroom
A Little Flexibility Frees a Lot of Grid
Duke University's Nicholas Institute found in February 2025 that the US grid could add 76 GW of new load if it accepted curtailment in 0.25% of hours, about 85 hours a year, rising to 126 GW at 1%. During curtailment, half the load would keep running most of the time.
Programs and rules
Flexible-Load Programs and Rules
| Program | Scale | Mechanism | Status |
|---|---|---|---|
| Google flexible-load contracts | 1 GW | Utility-called cut or shift of machine learning work | In contracts with five utilities, March 2026 |
| Emerald AI | 256-GPU demo; 96 MW Nvidia Aurora site, Manassas, VA | Software that schedules GPU jobs to hit a power target; cut 25% for three hours at the Phoenix evening peak with Oracle and SRP | 96 MW site under construction; $150M raised August 2026 |
| Texas SB 6 | Loads of 75 MW and up | ERCOT may order curtailment or disconnection of large loads in emergencies | Rules adopted September 2026 |
| Crusoe and Goodnight Wind, Texas | 260 MW | Full disconnect on ERCOT order with 60 minutes' notice; barred from ERCOT demand-response programs | Texas PUC order July 2026, first under SB 6 |
| PJM interim resource adequacy service | New loads of 50 MW and up | New load not backed by new capacity can be cut before PJM's emergency demand response | Filed at FERC August 2026; exposure from June 2027 |
| Nvidia GB300 NVL72 power smoothing | Up to 30% lower peak demand | Energy storage in power supplies, ramp limits and a power burner | Shipping since 2025 |
| Bitcoin miners (Riot Platforms) | More than 95% of load at peak | ERCOT power and demand-response credits; $31.7M in August 2023 | Long-running |
Record
Dataset Record
- Dataset
- Flexible data center load programs and grid rules
- Sources
- Google, Duke University Nicholas Institute, Emerald AI, PUCT, PJM, FERC, Nvidia, Riot Platforms, Utility Dive, Latitude Media, DatacenterDynamics, White & Case
- Last verified
- October 2026