Energy Orchestration

Flexible load and power management · Curtailment, scheduling and smoothing · Flagship: Google's 1 GW of flexible load

A data center that can cut its draw for a few hours a year is easier for a utility to connect than one that never can. Google now has 1 GW of curtailable machine learning load in contracts with five utilities, and a Duke study finds 0.25% curtailment would free about 76 GW of US grid headroom.

How much new data center load the US grid could absorb if data centers accept curtailment: 76 GW at 0.25% of hours, 98 GW at 0.5% and 126 GW at 1%, from a Duke University study, with Google's 1 GW of flexible load contracts for scale GRID HEADROOM IF DATA CENTERS FLEX DUKE UNIVERSITY, 2025 0.25% curtailment~85 hours a year 76 GW 0.5% curtailment~177 hours a year 98 GW 1% curtailment~366 hours a year 126 GW Google, March 2026flexible load in contracts 1 GW HOW GOOGLE FLEXES SignalUtility calls a grid-stress event ActionGoogle cuts or shifts ML training load UtilitiesI&M, TVA, Entergy Arkansas, Minnesota Power, DTE PausesTraining jobs, which Google calls not mission-critical
Google flexible load
1 GW
Utilities
5
Headroom at 0.25%
76 GW
Headroom at 1%
126 GW
Hub
Energy

Google's flexible load

Google Writes Curtailment Into Its Utility Contracts

  • Scale: on March 19, 2026, Google said it has 1 GW of demand response written into long-term contracts with US utilities: Indiana Michigan Power and TVA first (August 2025), then Entergy Arkansas, Minnesota Power and DTE Energy.
  • How it works: when a utility signals grid stress, Google cuts or shifts part of its machine learning work for certain hours or times of year; training jobs can pause where live services cannot.
  • Why utilities agree: Google says flexible load lets new data centers connect sooner than firm load would.
  • Not disclosed: curtailment hours, sites and MW per utility.
  • Background: a 2024 pilot with a Nebraska utility cut machine learning demand in three grid events; earlier, Google shifted YouTube video processing in Belgium and Taiwan.

See Google Project Tembo.

Grid headroom

A Little Flexibility Frees a Lot of Grid

Duke University's Nicholas Institute found in February 2025 that the US grid could add 76 GW of new load if it accepted curtailment in 0.25% of hours, about 85 hours a year, rising to 126 GW at 1%. During curtailment, half the load would keep running most of the time.

Programs and rules

Flexible-Load Programs and Rules

Flexible data center load
ProgramScaleMechanismStatus
Google flexible-load contracts1 GWUtility-called cut or shift of machine learning workIn contracts with five utilities, March 2026
Emerald AI256-GPU demo; 96 MW Nvidia Aurora site, Manassas, VASoftware that schedules GPU jobs to hit a power target; cut 25% for three hours at the Phoenix evening peak with Oracle and SRP96 MW site under construction; $150M raised August 2026
Texas SB 6Loads of 75 MW and upERCOT may order curtailment or disconnection of large loads in emergenciesRules adopted September 2026
Crusoe and Goodnight Wind, Texas260 MWFull disconnect on ERCOT order with 60 minutes' notice; barred from ERCOT demand-response programsTexas PUC order July 2026, first under SB 6
PJM interim resource adequacy serviceNew loads of 50 MW and upNew load not backed by new capacity can be cut before PJM's emergency demand responseFiled at FERC August 2026; exposure from June 2027
Nvidia GB300 NVL72 power smoothingUp to 30% lower peak demandEnergy storage in power supplies, ramp limits and a power burnerShipping since 2025
Bitcoin miners (Riot Platforms)More than 95% of load at peakERCOT power and demand-response credits; $31.7M in August 2023Long-running

Record

Dataset Record

Dataset
Flexible data center load programs and grid rules
Sources
Google, Duke University Nicholas Institute, Emerald AI, PUCT, PJM, FERC, Nvidia, Riot Platforms, Utility Dive, Latitude Media, DatacenterDynamics, White & Case