The campus
The Only French Gigawatt Project With a Signed Grid Connection
- Owners: MGX of Abu Dhabi, Bpifrance, Mistral AI and Nvidia, from the UAE-France agreement of February 2025.
- Grid: RTE, France's transmission operator, signed the first fast-track connection in January 2026: 240 MW by the end of 2027 and 700 MW by the end of 2029.
- Size: 11 buildings on 89 hectares, designed for up to 1,400 MW, with full build-out around 2033 and about €50B of investment, reported.
- Permits: building permit filed March 2026; the public inquiry, held May 2026, gave a favorable opinion. The prefect's final decision has not been reported.
- Not disclosed: chips, outside tenants and a power supply contract.
France's AI sites
Mistral Runs the One AI Cluster Already Ramping
| Project | Committed MW | Live MW | Owners | Status |
|---|---|---|---|---|
| Campus IAFouju, Seine-et-Marne | 240 by end 2027; 700 by end 2029; 1,400 design | 0 | MGX, Bpifrance, Mistral, Nvidia | First RTE fast-track contract (January 2026); public inquiry favorable; 11 buildings on 89 hectares |
| Mistral ComputeBruyères-le-Châtel, Essonne | About 44 | Ramping | Mistral, leased hall | 13,800 GB300; $830M bank debt (March 2026); 10 MW inference site at Les Ulis due Q3 2026 |
| E-Valley (Brookfield and Data4)Cambrai, former air base | 300 first phase; up to 1,000 | 0 | Brookfield, Data4 | Construction targeted for second half of 2026 |
| Fluidstack 1 GWLe Bosquel | Dropped | 0 | Fluidstack | Fluidstack left France to focus on the US (March 2026) |
Mistral is also a Campus IA shareholder. It targets 200 MW in Europe by 2027 and 1 GW by 2030.
Fast-track connections
France Requested 28.6 GW and Has 5.8 GW on Secured Sites
- Summit pledges: €109B was pledged at the February 2025 AI summit. A ministry review in January 2026 counted 13 companies with projects, 63 suitable sites, and 28.6 GW of capacity requested, of which 5.8 GW is tied to secured sites with connection commitments.
- Fast-track sites: five sites of more than 700 MW each, connectable within three to four years: Escaudain, Le Bosquel, Dunkirk port, Fouju and Montereau. The energy regulator approved the process in spring 2025.
- EDF land: EDF offered four sites of its own with about 2 GW in total in February 2025; no winning developers have been named.
- Nuclear power contracts: EDF and Data4 signed a 12-year nuclear supply contract for 40 MW, about 230 GWh a year, from 2026, the reference deal for French data centers.
See Nuclear Power and Grid Tie.
EU gigafactories
The EU Will Pick Up to Seven AI Gigafactories in 2027
- InvestAI: launched February 2025 to mobilize €200B, including €20B for AI gigafactories.
- Tender: opened July 30, 2026 for up to seven sites, four of at least 120 MW and three of at least 150 MW, with more than €30B in total: up to €10B public, at least €20B private. Only €1B is legally committed. Bids are due in November or December 2026; awards are expected early in 2027.
- AI Factories: 19 EuroHPC AI Factories plus 13 smaller satellite sites, built on national supercomputing centers.
Elsewhere in Europe
Hydro in Norway, Grid Waits in Britain
| Site | MW | Status |
|---|---|---|
| Narvik, NorwayNscale; Microsoft customer | 230, hydro | $6.2B Microsoft deal, expanded April 2026 with 30,000+ Rubin GPUs for 2027; formerly Stargate Norway |
| Sines, PortugalStart Campus | 26 live; 1,200 planned | Second building under construction; first customers 2027 |
| Munich, GermanyDeutsche Telekom Industrial AI Cloud | Not disclosed | Launched February 2026 with about 10,000 Nvidia Blackwell GPUs |
| Loughton, UKNscale | 50, expandable to 90 | Microsoft left the deal (October 2026); full grid power not until the early-to-mid 2030s |
| North East EnglandAI Growth Zone, QTS at Cambois | Not disclosed | Designated 2025; plan in consultation |
Grid limits
Amsterdam, Dublin and London Are Out of Grid Capacity
- Dublin: connection requests of about 1,200 MW are about three times what is available; data centers use about 21% of Ireland's electricity. Rules from late 2025 require new sites to bring their own generation and support grid flexibility.
- Amsterdam: 927 MW live, with connection waits over three years on congested TenneT and Liander networks and a city moratorium; a court ruled in April 2026 that Haarlemmermeer's grid is full.
- Frankfurt: 981 MW live.
- EU rating: in September 2026 the Commission adopted an EU-wide sustainability label for data centers of 500 kW or more of IT load, grading energy and water efficiency, energy sources and readiness for heat reuse.
Record
Dataset Record
- Dataset
- French and European AI campuses and grid connection status
- Sources
- RTE, French Ministry of the Economy, EDF, European Commission, EuroHPC, Nscale, Bloomberg, DatacenterDynamics, Maddyness, MesInfos, NL Times, LexisNexis
- Last verified
- October 2026