Microgrids

Islanded private grids · Generation, storage and load on one site · Flagship: GW Ranch, Pecos County, Texas

A private grid lets a campus skip the utility queue entirely, with its own turbines, batteries and solar. GW Ranch in West Texas, now Amazon's, holds a 7.65 GW gas permit and plans 1.8 GW of batteries and 750 MW of solar, with no connection to ERCOT.

GW Ranch private grid: two gas pipelines feed 35 turbines, with 1.8 GW of batteries and 750 MW of solar, on a private bus serving the data center with no ERCOT connection, and a possible later grid tie GW RANCH PRIVATE GRID, PECOS COUNTY SCHEMATIC 2 GAS PIPELINESFirm supply 35 GAS TURBINES~5 GW configured;7.65 GW permitted BATTERIES1.8 GW, by 2031MWh not disclosed SOLAR750 MW, by 2031Amazon exploring PRIVATE BUS AMAZON DATA CENTER8,000+ acres; load notdisclosed First power H1 2027; 1 GW 2028 ERCOT GRIDNo connection today;grid service under study RELIABILITY CLAIMFive nines (99.999%), developerSpare-turbine and black-startdesign not published PHASES H1 2027First power 20281 GW 20315+ GW, batteries, solar TCEQ: THE PLANT CANNOT SELL POWER TO, OR BUY FROM, THE LOCAL UTILITY.
Gas permitted
7.65 GW
Batteries planned
1.8 GW
Solar planned
750 MW
First power
First half of 2027
Hub
Energy

GW Ranch

An 8,000-Acre Campus With Its Own Grid

  • Developer: Pacifico Energy, about 17 miles north of Fort Stockton. Amazon confirmed in August 2026 that it acquired the site and will buy power from Pacifico.
  • Permit: the Texas Commission on Environmental Quality approved 7.65 GW of gas generation in January 2026; its preliminary determination describes 35 simple-cycle turbines with 5,000 MW of nominal output.
  • Full build: 5 GW of gas, 1.8 GW of batteries and 750 MW of solar by 2031. First power targeted for the first half of 2027, 1 GW in 2028.
  • Off-grid: gas arrives by two pipelines; the plant cannot sell to or buy from the local utility. Amazon is exploring a later move to grid service.
  • Water and emissions: no water for power-plant cooling in phase one, brackish groundwater later; permitted CO2-equivalent of about 33 million tons a year if every turbine ran all year.

See AWS GW Ranch on AustinIO and AWS Project Rainier.

Texas rules

Off-Grid Avoids the Grid Queue, Not the Air Permit

  • SB 6 (2025): set Texas standards for connecting loads of 75 MW and up, with emergency curtailment.
  • August 2026: Governor Abbott ordered an audit of data centers in ERCOT's queue and paused new connections until it is done.
  • September 2026: a second letter paused data center environmental approvals; watchdogs found preliminary approvals still issued the next day for Nexus Hubbard and a VoltaGrid plant.

Other private grids

Other Islanded and Private-Grid Campuses

Islanded and private-grid AI campuses
CampusPower planGrid status
Fermi America MatadorAmarillo, TXAbout 2 GW of gas units assembled; 17 GW claimed; nuclear later200 MW from Xcel's SPS
Nexus HubbardHill County, TXAbout 613 MW gas plus 153 MW diesel backupDoes not sell to the grid
Stargate Project JupiterDona Ana County, NMUp to 2.45 GW of Bloom fuel cellsIslanded; exempt from state rules until 2035
Joule Capital PartnersMillard County, UTCaterpillar gas engines; 1.1 GWh grid-forming battery; 455 MW firstEntirely off-grid
Sailfish Comanche CircleHood County, TXUp to 600 MW onsite gas first; 5 GW totalHybrid private and grid
Data CityWebb County, TXGas, wind and solar, hydrogen later; up to 5 GWOff-grid; Phase 1 listed as canceled

Record

Dataset Record

Dataset
Islanded and private-grid AI campuses: generation, storage and grid status
Sources
TCEQ, Pacifico Energy, Amazon, PUCT, Texas Governor's office, Cleanview, POWER, EnergyTech, Data Center Knowledge, KUT, DatacenterDynamics
Last verified
October 2026