GW Ranch
An 8,000-Acre Campus With Its Own Grid
- Developer: Pacifico Energy, about 17 miles north of Fort Stockton. Amazon confirmed in August 2026 that it acquired the site and will buy power from Pacifico.
- Permit: the Texas Commission on Environmental Quality approved 7.65 GW of gas generation in January 2026; its preliminary determination describes 35 simple-cycle turbines with 5,000 MW of nominal output.
- Full build: 5 GW of gas, 1.8 GW of batteries and 750 MW of solar by 2031. First power targeted for the first half of 2027, 1 GW in 2028.
- Off-grid: gas arrives by two pipelines; the plant cannot sell to or buy from the local utility. Amazon is exploring a later move to grid service.
- Water and emissions: no water for power-plant cooling in phase one, brackish groundwater later; permitted CO2-equivalent of about 33 million tons a year if every turbine ran all year.
See AWS GW Ranch on AustinIO and AWS Project Rainier.
Texas rules
Off-Grid Avoids the Grid Queue, Not the Air Permit
- SB 6 (2025): set Texas standards for connecting loads of 75 MW and up, with emergency curtailment.
- August 2026: Governor Abbott ordered an audit of data centers in ERCOT's queue and paused new connections until it is done.
- September 2026: a second letter paused data center environmental approvals; watchdogs found preliminary approvals still issued the next day for Nexus Hubbard and a VoltaGrid plant.
Other private grids
Other Islanded and Private-Grid Campuses
| Campus | Power plan | Grid status |
|---|---|---|
| Fermi America MatadorAmarillo, TX | About 2 GW of gas units assembled; 17 GW claimed; nuclear later | 200 MW from Xcel's SPS |
| Nexus HubbardHill County, TX | About 613 MW gas plus 153 MW diesel backup | Does not sell to the grid |
| Stargate Project JupiterDona Ana County, NM | Up to 2.45 GW of Bloom fuel cells | Islanded; exempt from state rules until 2035 |
| Joule Capital PartnersMillard County, UT | Caterpillar gas engines; 1.1 GWh grid-forming battery; 455 MW first | Entirely off-grid |
| Sailfish Comanche CircleHood County, TX | Up to 600 MW onsite gas first; 5 GW total | Hybrid private and grid |
| Data CityWebb County, TX | Gas, wind and solar, hydrogen later; up to 5 GW | Off-grid; Phase 1 listed as canceled |
Record
Dataset Record
- Dataset
- Islanded and private-grid AI campuses: generation, storage and grid status
- Sources
- TCEQ, Pacifico Energy, Amazon, PUCT, Texas Governor's office, Cleanview, POWER, EnergyTech, Data Center Knowledge, KUT, DatacenterDynamics
- Last verified
- October 2026