Colossus 1
Turbines First, Grid Later, in South Memphis
- Why turbines: in 2024 the site had 8 MW from the grid. SpaceXSI brought in portable turbines, including Solar Turbines SMT-130 units of about 16 MW, treating units in place under 364 days as exempt from permits.
- Peak: aerial photos in March and April 2025 showed 35 turbines, about 422 MW. The Southern Environmental Law Center cited potential NOx emissions of 1,200 to 2,000 tons a year.
- Permit: the Shelby County Health Department permitted 15 turbines for permanent use in July 2025; the county board dismissed an appeal in December 2025. EPA confirmed in January 2026 that large turbines need permits even for temporary use.
- Now: 12 turbines, about 198 MW, remain, alongside 150 MW of grid power from MLGW and TVA, a second 150 MW substation, and Tesla Megapacks. The campus has been leased to Anthropic since May 2026.
See SpaceX Colossus.
Southaven
A Power Plant Six Miles From the Data Center
- Site: SpaceXSI bought a former Duke Energy plant in Southaven, Mississippi, in July 2025 to power Colossus 2 in Memphis, which has no utility supply.
- Mobile turbines: Solar Titan 130 and Titan 350 and GE TM2500 units, rising from 18 in summer 2025 to 59 by May 2026, about 1.3 GW.
- Permanent plant: Mississippi's environmental agency permitted 41 turbines, about 1.2 GW, in March 2026: 17 Titan 130, 16 Titan 350 and eight ProEnergy PE6000.
- Settlement: after NAACP, SELC and Earthjustice sued, SpaceX agreed in August 2026 to remove all 69 mobile turbines by July 2027.
- Beyond 1 GW: a Solaris Energy Infrastructure joint venture targets more than 1.1 GW by mid-2027, and Doosan shipped its first 380 MW turbine for SpaceX in October 2026.
Other campuses
Behind-the-Meter Gas Across the US
Cleanview counts 59 data center projects planning about 90 GW of onsite generation; about 2 GW was running in mid-2026.
| Campus | Onsite MW | Equipment | Status |
|---|---|---|---|
| Microsoft Project KilbyPecos, TX | 2,670 | GE Vernova and Solar Turbines | Contract June 2026; investment decision end of 2026; first power 2028 |
| GW RanchPecos County, TX | 7,650 permitted | 35 gas turbines, model not stated | First power first half of 2027 |
| PORTS Technology CampusPiketon, OH | About 9,200 | Not named | Power by 2029 |
| Stargate AbileneAbilene, TX | About 1,000-1,200 | 29 GE LM2500XPRESS plus Solar Titan 350 | 360 MW from 10 turbines running January 2026 |
| Stargate FrontierShackelford County, TX | 2,580 | About 620 INNIO Jenbacher engines (VoltaGrid) | Under construction |
| Crusoe Abilene expansionAbilene, TX | 900 plus batteries | Not stated | First building mid-2027 |
| Meta PrometheusNew Albany, OH | 400 | Williams: Solar Titan and Siemens turbines, Caterpillar engines | Completion targeted Q3 2026 |
| Meta El PasoEl Paso, TX | 366 | 813 modular generators of about 450 kW | Online 2027 |
| Nexus HubbardHill County, TX | About 600-612 | Gas turbines | First building 2027; the 1.6 GW figure was not found in permits |
Turbine supply
Gas Turbines Are Sold Out to 2030
- GE Vernova: 116 GW of gas backlog and reservations in mid-2026; about 10 GW of slots were left for 2029-2030 by early 2026, and it now reserves 2031 delivery. New orders are priced 10 to 20 points higher than late 2025.
- Siemens Energy and Mitsubishi: 69 GW and 35 GW of backlog; three years or more to deliver.
- Prices: Wood Mackenzie projects turbines alone at $600/kW by end of 2027, about three times 2019; combined-cycle plants cost about $2,157/kW in 2025.
- Alternatives: reciprocating engines deliver in 24 to 36 months, with Caterpillar and Wärtsilä booked into 2028; fuel cells deliver faster still. See Hydrogen and Fuel Cells.
See Bottleneck Atlas.
Record
Dataset Record
- Dataset
- Behind-the-meter gas at AI campuses: units, MW, permits and status
- Sources
- Shelby County Health Department, Mississippi DEQ, MLGW, EPA, SELC, Cleanview, Tennessee Lookout, Action News 5, Gizmodo, Turbomachinery Magazine, Power Engineering, GE Vernova, company releases
- Last verified
- October 2026