Onsite Gas

Behind-the-meter gas · Turbines and engines on the campus · Flagship: Colossus gas turbines, Memphis and Southaven

Onsite gas lets an AI campus run before the grid can serve it, at the cost of air permits and lawsuits. SpaceXSI ran up to 35 turbines at Colossus 1 and 59 at Southaven for Colossus 2; Memphis has since shifted to the grid, and Southaven's mobile units must go by July 2027 as a permanent 1.2 GW plant is built.

Gas turbine counts at SpaceX Colossus sites over time: Colossus 1 in Memphis falling from 35 to 12 as grid supply arrived, Southaven rising to 59 mobile turbines before a settlement requires their removal by July 2027 and a 41-turbine permanent plant COLOSSUS GAS TURBINES ON SITE, COUNT 0 20 40 60 2025 2026 2027 COLOSSUS 1, MEMPHIS SOUTHAVEN, FOR COLOSSUS 2 41 permanent units, 1.2 GW Mobile units gone by July 2027 15 permitted, July 2025 WHAT REPLACED THE TURBINES AT COLOSSUS 1 Grid150 MW energized; second 150 MW substation built Turbines12 Solar SMT-130, about 198 MW BatteriesMegapacks; counts of 119 to 168 conflict SOUTHAVEN HAS NO UTILITY SUPPLY: ALL POWER IS ONSITE.
Colossus 1 peak
35 turbines, ~422 MW
Southaven peak
59 turbines, ~1.3 GW
Southaven permanent
41 units, 1.2 GW
US onsite planned
About 90 GW
Hub
Energy

Colossus 1

Turbines First, Grid Later, in South Memphis

  • Why turbines: in 2024 the site had 8 MW from the grid. SpaceXSI brought in portable turbines, including Solar Turbines SMT-130 units of about 16 MW, treating units in place under 364 days as exempt from permits.
  • Peak: aerial photos in March and April 2025 showed 35 turbines, about 422 MW. The Southern Environmental Law Center cited potential NOx emissions of 1,200 to 2,000 tons a year.
  • Permit: the Shelby County Health Department permitted 15 turbines for permanent use in July 2025; the county board dismissed an appeal in December 2025. EPA confirmed in January 2026 that large turbines need permits even for temporary use.
  • Now: 12 turbines, about 198 MW, remain, alongside 150 MW of grid power from MLGW and TVA, a second 150 MW substation, and Tesla Megapacks. The campus has been leased to Anthropic since May 2026.

See SpaceX Colossus.

Southaven

A Power Plant Six Miles From the Data Center

  • Site: SpaceXSI bought a former Duke Energy plant in Southaven, Mississippi, in July 2025 to power Colossus 2 in Memphis, which has no utility supply.
  • Mobile turbines: Solar Titan 130 and Titan 350 and GE TM2500 units, rising from 18 in summer 2025 to 59 by May 2026, about 1.3 GW.
  • Permanent plant: Mississippi's environmental agency permitted 41 turbines, about 1.2 GW, in March 2026: 17 Titan 130, 16 Titan 350 and eight ProEnergy PE6000.
  • Settlement: after NAACP, SELC and Earthjustice sued, SpaceX agreed in August 2026 to remove all 69 mobile turbines by July 2027.
  • Beyond 1 GW: a Solaris Energy Infrastructure joint venture targets more than 1.1 GW by mid-2027, and Doosan shipped its first 380 MW turbine for SpaceX in October 2026.

Other campuses

Behind-the-Meter Gas Across the US

Cleanview counts 59 data center projects planning about 90 GW of onsite generation; about 2 GW was running in mid-2026.

Behind-the-meter gas at AI campuses
CampusOnsite MWEquipmentStatus
Microsoft Project KilbyPecos, TX2,670GE Vernova and Solar TurbinesContract June 2026; investment decision end of 2026; first power 2028
GW RanchPecos County, TX7,650 permitted35 gas turbines, model not statedFirst power first half of 2027
PORTS Technology CampusPiketon, OHAbout 9,200Not namedPower by 2029
Stargate AbileneAbilene, TXAbout 1,000-1,20029 GE LM2500XPRESS plus Solar Titan 350360 MW from 10 turbines running January 2026
Stargate FrontierShackelford County, TX2,580About 620 INNIO Jenbacher engines (VoltaGrid)Under construction
Crusoe Abilene expansionAbilene, TX900 plus batteriesNot statedFirst building mid-2027
Meta PrometheusNew Albany, OH400Williams: Solar Titan and Siemens turbines, Caterpillar enginesCompletion targeted Q3 2026
Meta El PasoEl Paso, TX366813 modular generators of about 450 kWOnline 2027
Nexus HubbardHill County, TXAbout 600-612Gas turbinesFirst building 2027; the 1.6 GW figure was not found in permits

Turbine supply

Gas Turbines Are Sold Out to 2030

  • GE Vernova: 116 GW of gas backlog and reservations in mid-2026; about 10 GW of slots were left for 2029-2030 by early 2026, and it now reserves 2031 delivery. New orders are priced 10 to 20 points higher than late 2025.
  • Siemens Energy and Mitsubishi: 69 GW and 35 GW of backlog; three years or more to deliver.
  • Prices: Wood Mackenzie projects turbines alone at $600/kW by end of 2027, about three times 2019; combined-cycle plants cost about $2,157/kW in 2025.
  • Alternatives: reciprocating engines deliver in 24 to 36 months, with Caterpillar and Wärtsilä booked into 2028; fuel cells deliver faster still. See Hydrogen and Fuel Cells.

See Bottleneck Atlas.

Record

Dataset Record

Dataset
Behind-the-meter gas at AI campuses: units, MW, permits and status
Sources
Shelby County Health Department, Mississippi DEQ, MLGW, EPA, SELC, Cleanview, Tennessee Lookout, Action News 5, Gizmodo, Turbomachinery Magazine, Power Engineering, GE Vernova, company releases
Last verified
October 2026