Cape Station
The First Utility-Scale Enhanced Geothermal Plant
- First power: Cape Station synced to the grid on September 24, 2026, and Fervo declared commercial operation of its first 33 MW unit on September 30, the first utility-scale enhanced geothermal system to do so.
- Phases: two more 33 MW units by January 2027 complete the 100 MW first phase; a 400 MW second phase of eight 50 MW units is under construction for 2028. Fervo targets 1.1 GW by 2030, and its permits allow 2 GW.
- Drilling: its Sawtooth 7 well reached about 19,500 feet into rock near 460°F in 21 days, a company record, using oil-and-gas horizontal drilling.
- Buyers: about 900 MW is contracted, including Southern California Edison (320 MW), Shell (31 MW) and Google, whose 396 MW deal (September 2026) is the largest enhanced geothermal contract yet, with an option for about 600 MW more by June 2030 for a possible Utah data center.
- Money: Fervo listed on Nasdaq in May 2026, raising about $2.2B; the second phase costs about $5,500/kW against a long-term target of $3,000/kW.
Other deals
Geothermal Deals for Data Centers
| Deal | MW | Status |
|---|---|---|
| Ormat and GoogleNevada, under NV Energy's Clean Transition Tariff | Up to 150 | Plants online 2028-2030; state approval expected late 2026 |
| Fervo Corsac Station and GoogleNevada, NV Energy tariff | 115 | Pre-construction; tariff approved May 2025 |
| Sage Geosystems and MetaEast of the Rockies, site not chosen | Up to 150 | First phase targeted 2027; no 2026 update |
| XGS Energy and MetaNew Mexico, PNM grid | 150 | Both phases by 2030 |
| Ormat and SwitchSalt Wells, near Fallon, NV | About 13 | 20 years from 2030; Ormat's first data center contract |
| Quaise Energy, Project ObsidianNewberry area, Oregon | 50, scaling to 250 | Superhot rock; first power by 2030; no data center buyer confirmed |
| Microsoft and Contact EnergyTe Huka 3, New Zealand | 51.4 | Signed 2022 |
| Microsoft and G42, OlkariaKenya | 100 first, 1 GW goal | Stalled: Kenya refused capacity payments (2026) |
| MSB Matrix campusSulphur Springs, TX | 1,200 geothermal claimed, with 800 MW of Bloom fuel cells | Company claim; Phase 1 listed as canceled |
The MSB Matrix campus in Hopkins County, Texas, claimed 800 MW of Bloom fuel cells followed by a 1,200 MW geothermal microgrid. No geothermal developer is named, East Texas lacks the hot rock found in the Great Basin, and Cleanview lists its first phase as canceled.
Why it fits
Firm Power, but Only Where the Rock Is Hot
- Firm output: geothermal runs around the clock; new plants are designed for capacity factors above 90%.
- Location: the best resource is in the Great Basin, Utah and Nevada, so data centers buy through utility tariffs such as NV Energy's Clean Transition Tariff or Utah's direct-to-load path, or move to the resource. Sage and Quaise aim to widen the map.
- Policy: the July 2025 tax law kept full investment and production tax credits for geothermal projects that start construction by 2033, long after wind and solar lose theirs.
Record
Dataset Record
- Dataset
- Geothermal supply contracted by data center companies
- Sources
- Fervo Energy, SEC filings, Google, Ormat, Meta, NV Energy, Cleanview, ThinkGeoEnergy, Power Engineering, Latitude Media, Utility Dive, DatacenterDynamics
- Last verified
- October 2026