Claims and commitments
The Headline Figures Measure Generation, Not Data Centers
Both of Fermi's headline numbers count power plants it plans to build. Neither is a data center load, and Fermi has not published an IT load for the campus.
- 11 GW: the "private HyperGrid" figure at the October 2025 IPO, mostly gas.
- About 17 GW: raised in March 2026. It depends on buying adjacent land, which would take the campus to about 8,400 acres, and on more air permits.
- About 6 GW of gas holds a final air permit from the Texas Commission on Environmental Quality (February 2026). A request for about 5 GW more, filed in March, has no decision.
- About 15 million sq ft of data center space is planned.
- 2 GW of gas plus grid by the end of 2027 replaced an earlier target of 1.1 GW online by the end of 2026.
Under the committed-capacity rule used on Largest Data Centers in the US, Matador is not ranked: the only commitment is the TensorWave lease, and it has not closed.
The tenant
One Lease, Signed but Not Yet in Force
- First prospect walked away: an unnamed investment-grade tenant signed a construction-funding advance of up to $150M in November 2025, then terminated it on December 11 without drawing any money. The stock fell about 34% that day.
- TensorWave lease, August 9, 2026: 222 MW of total facility power, about $6.5B over a 15-year term with two five-year renewals. An option for two more buildings would take it to 650 MW. Delivery runs in phases from late 2027 into early 2028.
- AMD credit support, October 13, 2026: AMD will guarantee part of TensorWave's obligations on the first 222 MW and signed a non-binding framework for later phases up to 650 MW. The guaranty amount is not disclosed.
- Closing: the lease takes effect only once guaranties, an operations schedule, a service-level agreement, board approvals and project financing are in place. The closing date moved from September 30 to October 31, 2026.
TensorWave plans "tens of thousands" of AMD Instinct GPUs; the model is not named.
Power
A Private Grid Assembled From New, Used and Leased Turbines
- Gas and grid
- Nuclear
- Solar and batteries
| Source | MW | Status |
|---|---|---|
| SPS grid service (Xcel Energy) | Up to 200 | Contract signed December 2025: 86 MW in the second half of 2026, the rest by October 2027 |
| Siemens SGT-800, first six turbines | About 300 | Arrived at Port of Houston February 2026; heat-recovery and steam equipment for combined cycle |
| Siemens SGT-800, second six | Not stated | Ordered October 2025 for 2028 delivery; $165M equipment loan |
| Siemens SGT6-5000F, three turbines | About 720 | $500M MUFG loan; cores due to ship mid-2026 |
| GE Frame 6B, three refurbished turbines | About 114 | Being restored in Houston |
| GE TM2500 mobile turbines, seven | About 158 | Leased; pickup July to September 2027 |
| Hillcore Energy Capital gas plant | About 2,500 | Framework August 2026: Hillcore would finance, build, own and run it; final contracts not signed |
| Westinghouse AP1000 reactors, four | About 4,400 | License application at the NRC; draft environmental review September 2026; no safety-review schedule |
| Solar and batteries | Not stated | Mainly third-party solar contracts; batteries planned for the first phase |
Energy Transfer supplies gas under a firm contract scaling to about 300,000 MMBtu a day; the site sits near the Transwestern and ONEOK pipelines, and 4.6 miles of onsite gas line are installed. See Onsite Gas.
Nuclear
Four AP1000s Are in Licensing, With No Decision Date
- Application: combined license for four Westinghouse AP1000 reactors filed June 2025; the NRC accepted the first two parts in September 2025. Fermi withdrew the site-specific part.
- Environmental review: draft environmental impact statement issued September 30, 2026; public comments close November 23; final statement targeted for December 2026.
- Safety review: no schedule or decision date set.
- Partners: Hyundai Engineering and Construction holds the front-end engineering contract; Doosan Enerbility signed a forging-readiness agreement.
- Small modular reactors: mentioned only "if commercially available," with no agreements.
See Nuclear Power.
The site
Texas Tech Land, Amarillo Water, and No Data Hall Yet
- Land: a 99-year Texas Tech lease, signed May 2025, covering about 5,236 acres. Base rent is $1.2M in year one; variable rent can reach 1% of data center value, 1% of power revenue and 25% of water revenue.
- Water: the City of Amarillo sells up to 2.5 million gallons a day at twice its industrial rate, with a non-binding path to 10 million. Six 30-year groundwater leases cover about 5,227 acres. Fermi plans hybrid dry and wet cooling and claims about 80% less water use.
- Built so far: about 261 acres cleared, 7.2 miles of water line, a 2-million-gallon tank, about 5 miles of onsite power lines and 11.3 miles of fencing. Work paused in February 2026 while the air permit was pending; satellite images from April 2026 show no data center buildings.
- Next: vertical construction starts after the first lease closes.
See Fermi America Data Center on AustinIO.
The company
A Public Company With a Going-Concern Warning
- IPO: priced September 30, 2025, at $21 a share, raising $682.5M at about a $12.5B valuation, listed on Nasdaq and the London Stock Exchange.
- Stock: about $3 in late October 2026, a market value near $1.9B and down about 89% over the year.
- Balance sheet, June 30, 2026: $62.5M cash and $537M of debt. The quarterly filing flags substantial doubt about Fermi continuing as a going concern. Fermi issued $431M of convertible notes in July, and in October paid $25M in fees to drop a lender's requirement to sign 400 MW of leases by November 10.
- Leadership: co-founder and CEO Toby Neugebauer was removed in April 2026 and fired for cause; the CFO resigned. Lee McIntire became CEO in August. Former Energy Secretary Rick Perry, a co-founder, remained a director as of May.
- Litigation: an IPO securities class action, Neugebauer's suit in the Texas Business Court, and several turbine and equipment claims.
Deadlines
Five Dates Decide Whether Matador Gets Built
- October 31, 2026: TensorWave lease must close.
- November 12, 2026: third-quarter results.
- November 23, 2026: NRC environmental comment period closes.
- December 31, 2026: Texas Tech must give notice to proceed, which requires a first-phase lease of at least 200 MW.
- Late 2027 to early 2028: first TensorWave delivery.
Record
Dataset Record
- Dataset
- Fermi America lease, power sources and deadlines; Matador also listed under announced claims on Largest Data Centers in the US
- Sources
- Fermi America 10-K and 10-Q filings and releases, NRC docket, Federal Register, DatacenterDynamics, Bisnow, TechCrunch, ABC7 Amarillo, Cleanview, Benzinga
- Last verified
- October 2026