Five Gigawatt Campuses, Two of Them Owned Mostly by Investors
Hyperion in Louisiana is Meta's largest campus and the largest committed AI campus in the US. Four more campuses of 1 GW or more are operating or under construction.
- Meta-owned or Meta-run
- Investor-owned share
- Leased from a landlord
| Campus | Committed MW | Ownership | Energy | Status |
|---|---|---|---|---|
| Meta HyperionRichland Parish, LA | 5,000 | Blue Owl joint venture owns 80%; Meta 20% and tenant | Grid plus gas plants Entergy is building | Under construction; first 2 GW by 2030, 5 GW around 2032 |
| Meta PrometheusNew Albany, OH | 1,000 | Meta | Grid plus onsite gas plants built by Williams | Partly operating, including tent buildings |
| Meta El PasoEl Paso, TX | 1,000 | BlackRock joint venture owns 80%; Meta 20% and tenant | Grid plus El Paso Electric's planned 366 MW McCloud gas plant | Under construction; first capacity 2028 |
| Meta LebanonLebanon, IN | 1,000 | Meta | Grid | Under construction |
| Meta Sturgeon CountySturgeon County, AB, Canada | 1,000 | Meta | 932 MW Greenlight gas plant plus Capital Power | Ground broken July 2026 |
| Reliance JamnagarJamnagar, Gujarat, India | 168 | Reliance; Meta leases | Reliance solar | Under construction |
| Meta TempleTemple, TX | Not disclosed | Meta | Grid, matched by a 240 MW Texas solar contract | Live July 2026; first site with Meta's AI-optimized design |
Temple is far smaller than the gigawatt campuses; Meta has not published its power, and a third-party database lists about 152 MW. It matters as the first site to go live with Meta's AI-optimized design.
Financing
Investors Own 80% of Hyperion and El Paso
- Hyperion: a joint venture vehicle, Beignet Investor, issued about $27B of bonds in October 2025. Blue Owl put in about $3B for 80%; Meta holds 20% and rents the campus. Meta expanded Hyperion to 5 GW in July 2026, with up to $50B of investment: the first 2 GW by 2030, the full 5 GW around 2032.
- El Paso: BlackRock funds took 80% of the $14B, 1 GW project in July 2026. Meta contributed about $2.3B of assets, BlackRock about $4.9B in cash, and Meta received a $1B distribution.
- Capital spending: Meta guides to $135-145B for 2026, including finance-lease principal.
The structure keeps the debt off Meta's balance sheet while Meta designs, operates and fills the buildings. See Business Models and Ownership.
Rented compute
Meta Also Rents Compute From Clouds
| Provider | Contract | Notes |
|---|---|---|
| Google Cloud | More than $10B over six years (August 2025), plus TPU rental (February 2026) | Meta reportedly could not get all the Google capacity it wanted |
| CoreWeave | $21B through December 2032 (April 2026) | Expands a $14.2B contract from September 2025 |
| Nebius | Up to $27B over five years (March 2026) | $12B firm; Nvidia Vera Rubin capacity from early 2027 |
| Reliance | 168 MW first phase at Jamnagar (June 2026) | Built by Reliance, leased by Meta |
| Cloud and colocation overall | More than 5 GW contracted in the first half of 2026 | SemiAnalysis; counterparties not named |
Meta also began selling surplus AI compute in July 2026, reports say.
Where Muse trains
Prometheus Trains Meta's Muse Models
- Prometheus in New Albany, Ohio, holds Meta's largest training cluster: several hundred thousand Nvidia GPUs, with a target of about 1 million. Part of it runs in tent-like "rapid deployment structures" powered by onsite gas turbines.
- Muse Spark, the first model from Meta Superintelligence Labs, launched April 8, 2026. Meta says the first phase of Prometheus trained its Muse foundation models, without naming Spark separately; where Meta serves Meta AI is not disclosed.
- Muse Wonder, released October 12, 2026, was trained at Prometheus, Meta says.
- Muse Spark Open, the open-weight release of October 15, 2026, is hosted by Baseten, Fireworks AI, Modal, Nebius, OpenRouter and Together AI, with Groq in limited preview, and is downloadable on Hugging Face, Amazon SageMaker, Google Cloud and Microsoft Foundry.
The wider fleet
33 Data Centers, Most Serving Facebook, Instagram and WhatsApp
Meta called Sturgeon County, Alberta, the 33rd data center in its fleet when it broke ground in July 2026. It does not publish how many are built for AI. A third-party count tags about 12 as AI-optimized; the rest mainly serve and store traffic for Facebook, Instagram, WhatsApp and Messenger.
Meta paused Temple and Kuna, Idaho, in late 2022 to redesign them for denser AI hardware. Meta said in 2022 that the new design would cost 31% less and take half as long to build; Temple was the first to go live with it, in July 2026.
Power
Utilities and Partners Build Gas Plants for Meta
- Hyperion: Entergy Louisiana is building gas plants for the campus; the first, Franklin Farms at about 1.5 GW, is due by the end of 2028, and plants for the 5 GW expansion await state approval. Meta also funds renewables, batteries and nuclear uprates.
- Prometheus: an AEP Ohio grid tie plus gas plants built by Williams under a 10-year deal.
- El Paso: El Paso Electric's planned 366 MW McCloud gas plant, to be built and run by Enchanted Rock for a 2027 target, is awaiting approval from the Public Utility Commission of Texas.
- Sturgeon County: the 932 MW Greenlight combined-cycle gas plant, plus 250 MW from Capital Power from 2028.
- Lebanon: grid power, with Meta paying the full energy cost.
See Onsite Gas.
Record
Dataset Record
- Dataset
- Meta campuses and compute contracts; campus rows also in us_ai_campuses.csv and world_ai_campuses.csv
- Sources
- Meta, Epoch AI, DatacenterDynamics, CNBC, Forbes, Data Center Frontier, The Next Web, Capacity Global, SemiAnalysis, Fox 8, KWTX