PORTS Technology Campus

AI on federal land · DOE Portsmouth Site, Piketon, Ohio · SB Energy, a SoftBank company

The Energy Department is leasing former nuclear-weapons and uranium sites to private developers for AI data centers that bring their own power. The 10 GW PORTS Technology Campus on the old Portsmouth uranium enrichment site is the only one to break ground; most of the power planned across these sites is gas, not the nuclear DOE said it preferred.

Federal sites offered for private AI data centers and how far each has progressed: solicited, developer picked, terms set, ground broken, operating. Only Portsmouth, Ohio has broken ground; none is operating. AI DATA CENTERS ON FEDERAL LAND: HOW FAR EACH HAS GOT MW BIDS PICKED TERMS GROUND LIVE Portsmouth, OHDOE10,000 Paducah, KYDOE1,800 Savannah River, SCDOE1,000 Idaho National LabDOEn/d Oak Ridge, TNDOEn/d Fort Bliss, TXArmyn/d Dugway, UTArmyn/d Three Alaska basesAir Forcen/d Done Conditional or pending Not yet BIDS: SOLICITED. PICKED: DEVELOPER CHOSEN. TERMS: LEASE AND POWER DEAL SET.DOE TARGET IN APRIL 2025: GROUND BROKEN BY END OF 2025, OPERATING BY END OF 2027.
PORTS campus
10 GW
New generation
Up to 10 GW, 9.2 GW gas
Ground broken
March 2026
Sites solicited
5 DOE, 5 military
Sites operating
None
Hub
Deployments

PORTS campus

A 10 GW Campus on a Former Uranium Enrichment Site

  • Site: the DOE Portsmouth Site in Piketon, Ohio, a former gaseous diffusion uranium enrichment plant. It was among the 16 candidate sites DOE listed in April 2025 but not among the four picked in July; it advanced separately in March 2026.
  • Developer: SB Energy, a SoftBank company, with AEP Ohio as utility partner. The first phase covers 189 acres.
  • Power: up to 10 GW of new generation, 9.2 GW of it gas. Financing named so far: $4.2B for transmission and $33.3B of Japanese funding for the gas plants.
  • Status: ground broken March 20, 2026, with about 10,000 construction jobs and more than 2,000 permanent jobs projected.

See Onsite Gas.

All federal sites

Three DOE Sites Have Developers; Two Have None a Year Later

  • DOE, developer named
  • DOE, no award
  • Military land
Federal sites offered for AI data centers
SiteDeveloperMW and powerStatus
Portsmouth (PORTS Technology Campus)Piketon, OHSB Energy (SoftBank); AEP Ohio10,000 campus; up to 10 GW new generation, 9.2 GW of it gasGround broken March 20, 2026
PaducahPaducah, KYBrookfield (campus); NextEra (power)1,800 AI campus; 2 GW new gas; up to 2.6 GW batteriesSelected July 29, 2026; power deal awaits Kentucky PSC; completion 2031
Savannah River SiteAiken, SCAmentum1,000 data center; about 2 GW onsite, gas first, then nuclearSelected for lease negotiation July 2026; not a final award
Idaho National LaboratoryNear Idaho Falls, IDNone announcedNot foundApplications closed November 2025; no award
Oak Ridge ReservationOak Ridge, TNNone announcedNot found; about 245 acres near TVA 500 kV linesProposals closed December 2025; no award
Fort BlissEl Paso, TXCarlyle, conditionally selectedNot disclosed; about 1,384 acresArmy lease in negotiation; initial operation fiscal 2027
Dugway Proving GroundUtahCyrusOne, conditionally selectedNot disclosed; about 1,201 acresArmy lease in negotiation; initial operation fiscal 2029
Elmendorf-Richardson, Eielson, ClearAlaskaNone selectedNot disclosed; about 4,700 acresAir Force request for proposals April 2026

Lease terms

Developers Pay for Everything, Including the Power Plant

DOE leases its sites "as is, where is." The developer designs, finances, permits, builds, runs and eventually removes the data center, and new generation must be part of the project; DOE said it prefers nuclear or geothermal. DOE expected six to 18 months of development, one to two years of construction and at least 10 years of operation. Rents and terms are negotiated after award and none has been published. Army sites use enhanced use leases with no upfront cost to taxpayers.

Executive orders

Permitting Shortcuts for Projects Over 100 MW

  • EO 14141 (January 2025): directed DOE and the Defense Department to lease federal sites for AI data centers with clean power. Revoked by EO 14318.
  • EO 14318, Accelerating Federal Permitting of Data Center Infrastructure (July 2025): covers projects with more than 100 MW of new AI load or at least $500M of capital spending. It orders new categorical exclusions from environmental review, treats federal funding below 50% of cost as not a "major federal action," and directs agencies to offer leases on their sites.

Genesis Mission

Genesis Puts AI to Work Across All 17 National Labs

  • Order: EO 14363, November 24, 2025, launched an AI platform for science across the 17 national labs, aiming to double US research productivity within a decade.
  • Partners: 24 organizations signed on in December 2025, including Nvidia, AMD, Anthropic, OpenAI, Google, Microsoft, AWS, Oracle, SpaceXSI, HPE, Dell, IBM, Intel, Cerebras, Groq, CoreWeave and Palantir.
  • Funding: $320M+ across four initiatives in December 2025, including $150M for an American Science Cloud. At the first Genesis summit in July 2026, partners committed more than $800M.
  • Compute: half of Oak Ridge's new Lux AI cluster goes to Genesis work. See Oak Ridge National Laboratory.

Obstacles

Gas Instead of Nuclear, Contaminated Land, Slipping Dates

  • Fuel: Portsmouth's power is mostly gas, Paducah's plan names gas and batteries, and Savannah River starts on gas, against DOE's stated preference for nuclear and geothermal.
  • Contamination: cleanup at Paducah runs to 2065 at about $17B; the Kentucky Resources Council wants close oversight of building on and pumping water from the site.
  • Local opposition: a Paducah group says no study covers the effect on a river supplying about 5 million people downstream; Ohio residents filed a petition for a constitutional ban on mega data centers.
  • Schedule: DOE targeted ground broken by the end of 2025 and operation by the end of 2027; Idaho and Oak Ridge have no award a year after bids closed.
  • Congress: a House bill, H.R. 9939, would bar AI data centers on federal land, including military bases.

Record

Dataset Record

Dataset
Federal-land AI data center sites: developer, power plan and stage reached
Sources
US Department of Energy, NNSA, US Army, Federal Register, White House executive orders, AP, American Nuclear Society, NucNet, Perkins Coie, DatacenterDynamics, UK Defence Journal
Last verified
October 2026