Entergy and Hyperion
A Utility Builds a Gas Fleet for One Campus
- First package: Louisiana regulators approved three 754 MW combined-cycle gas units, 2,262 MW, on August 20, 2025, by a 4-1 vote: two near the campus in late 2028 and one at Waterford in late 2029, about $3.2B for the plants and about $5B for Entergy's whole package.
- Transmission: a 100-mile, 500 kV line costing $1.2B, two new substations, six customer-owned substations and eight new 230 kV lines; Meta pays for the 55-acre Smalling substation.
- Contract: 15 years with a Meta subsidiary, guaranteed by Meta. Minimum bills cover the full cost of the new units during the term; the exit fee does not cover full project cost. Meta also pays for 1,500 MW of solar.
- Expansion: filed March 2026 for Meta's 5 GW build: seven more gas units of about 754 MW, three battery projects and more than 250 miles of lines, at $12.9B to $16B by different counts, under a 20-year agreement. Hearings ran October 7-9, 2026; the vote is set for December 16.
- Critics: the Alliance for Affordable Energy, Union of Concerned Scientists and Sierra Club argue a 15- or 20-year contract on 30-year plants leaves ratepayers with stranded cost, and appealed a ruling that blocked a subpoena of Meta data.
See Meta Hyperion.
Large-load tariffs
Utilities Now Make Data Centers Pay Up Front
Utilities across the US have written special rate classes so data centers carry the cost of the plants and lines built for them, mostly through minimum bills, long contracts and exit fees.
| Utility or rule | Size | Mechanism | Status |
|---|---|---|---|
| AEP Ohio data center tariff | Above 25 MW | Pay for 85% of subscribed capacity whether used or not; up to 12 years; exit fees | Ohio order July 2025; in effect |
| Dominion Virginia high-load class | Above 25 MW at 75% load factor | Minimum 85% of transmission and distribution and 60% of generation demand; 14-year contracts; 944 MW Chesterfield gas plant | Virginia order November 2025 |
| Georgia Power | 9,885 MW certified | Utility builds for expected 2029-2031 load; certification can be reversed if contracts are not signed | Georgia PSC December 2025 |
| We Energies very large customer tariff | Above 100 MW; Microsoft ~2,600 MW | Customer pays 100% of generation built for it; 15-year minimum; Oak Creek and Paris gas plants | Wisconsin PSC April 2026. See Microsoft Fairwater |
| NIPSCO generation affiliate | Amazon 2,800 MW by 2032 | Affiliate builds two 1.3 GW gas plants and 400 MW of batteries and sells to NIPSCO; 15 years; ~$1.4B bill credits to other customers | Indiana order June 2026. See AWS Project Rainier |
| Entergy Mississippi | Traceview gas plant, 754 MW | AWS prepaid equipment, transmission and substations | Under construction, 2029 |
| Xcel Energy | 2 GW contracted; Google ~1 GW in Minnesota | Large-load tariffs with long contracts, exit fees and credit requirements in four states | Google deal pending |
| Texas SB 6 and PUCT rule | 75 MW and above | $100,000 study fee; $50,000 per MW security; emergency curtailment of large loads | Adopted September 2026; data center permits paused by the governor |
| PJM | New loads 50 MW and up | Backstop procurement; bring-your-own generation; curtailable connect-and-manage option | Being implemented |
National picture
Data Centers Are Most New US Load
- Load growth: Grid Strategies forecasts 166 GW of summer peak growth from 2025 to 2030, about 90 GW of it from data centers.
- Queues: ERCOT had more than 233 GW of large-load requests at the end of 2025, over 70% data centers; AEP Ohio alone has more than 30 GW of inquiries. See Scaling Data Center Energy.
- FERC: in June 2026 FERC ordered six grid operators to justify or reform their rules for loads of 50 MW and up above 69 kV, covering cost shifting, flexible service and generation sited near the load.
Record
Dataset Record
- Dataset
- Utility-built generation and large-load tariffs for data centers
- Sources
- Louisiana PSC, Ohio PUCO, Virginia SCC, Georgia PSC, Wisconsin PSC, Indiana URC, PUCT, PJM, FERC, Entergy, Louisiana Illuminator, S&P Global, DatacenterDynamics, Utility Dive, POWER
- Last verified
- October 2026