Grid-Tie

Utility power for AI campuses · Utility-built plants, large-load tariffs, grid rules · Flagship: Entergy Louisiana for Meta Hyperion

Most AI campuses still take their power from the utility, but the utility now builds plants for one customer. Entergy Louisiana is building 2,262 MW of gas for Meta Hyperion, with about 5,278 MW more up for a vote in December 2026, under a contract shorter than the plants' lives.

Entergy Louisiana generation for Meta Hyperion: 2,262 MW of gas approved in 2025, 5,278 MW more pending a December 2026 vote, and 1,500 MW of solar Meta pays for; and the 15-year contract against a gas plant life of about 30 years ENTERGY'S BUILD FOR META HYPERION, MW Approved Aug 20253 gas units, 2,262 MW In service 2028-2029 Pending, vote Dec 167 gas units, ~5,278 MW Plus 3 battery projects Meta-funded solar1,500 MW committed Solar or solar plus storage If approved: 10 gas units, ~7.5 GW, plus renewables and storage WHO PAYS AFTER THE CONTRACT ENDS 2028 2038 2048 2058 META CONTRACT, 15 YEARS GAS PLANT LIFE, ~30 YEARS Costs after 2043: open question Meta's minimum bills cover the new plants during the term. The exit fee doesnot cover full cost, and critics say ratepayers carry what remains. TRANSMISSION: 100-MILE 500 KV LINE, $1.2B, PLUS 250+ MILES IN THE EXPANSION
Approved for Hyperion
2,262 MW gas
Pending
~5,278 MW gas
Meta contract
15 years
New 500 kV line
100 miles
Hub
Energy

Entergy and Hyperion

A Utility Builds a Gas Fleet for One Campus

  • First package: Louisiana regulators approved three 754 MW combined-cycle gas units, 2,262 MW, on August 20, 2025, by a 4-1 vote: two near the campus in late 2028 and one at Waterford in late 2029, about $3.2B for the plants and about $5B for Entergy's whole package.
  • Transmission: a 100-mile, 500 kV line costing $1.2B, two new substations, six customer-owned substations and eight new 230 kV lines; Meta pays for the 55-acre Smalling substation.
  • Contract: 15 years with a Meta subsidiary, guaranteed by Meta. Minimum bills cover the full cost of the new units during the term; the exit fee does not cover full project cost. Meta also pays for 1,500 MW of solar.
  • Expansion: filed March 2026 for Meta's 5 GW build: seven more gas units of about 754 MW, three battery projects and more than 250 miles of lines, at $12.9B to $16B by different counts, under a 20-year agreement. Hearings ran October 7-9, 2026; the vote is set for December 16.
  • Critics: the Alliance for Affordable Energy, Union of Concerned Scientists and Sierra Club argue a 15- or 20-year contract on 30-year plants leaves ratepayers with stranded cost, and appealed a ruling that blocked a subpoena of Meta data.

See Meta Hyperion.

Large-load tariffs

Utilities Now Make Data Centers Pay Up Front

Utilities across the US have written special rate classes so data centers carry the cost of the plants and lines built for them, mostly through minimum bills, long contracts and exit fees.

Utility deals and rules for large loads
Utility or ruleSizeMechanismStatus
AEP Ohio data center tariffAbove 25 MWPay for 85% of subscribed capacity whether used or not; up to 12 years; exit feesOhio order July 2025; in effect
Dominion Virginia high-load classAbove 25 MW at 75% load factorMinimum 85% of transmission and distribution and 60% of generation demand; 14-year contracts; 944 MW Chesterfield gas plantVirginia order November 2025
Georgia Power9,885 MW certifiedUtility builds for expected 2029-2031 load; certification can be reversed if contracts are not signedGeorgia PSC December 2025
We Energies very large customer tariffAbove 100 MW; Microsoft ~2,600 MWCustomer pays 100% of generation built for it; 15-year minimum; Oak Creek and Paris gas plantsWisconsin PSC April 2026. See Microsoft Fairwater
NIPSCO generation affiliateAmazon 2,800 MW by 2032Affiliate builds two 1.3 GW gas plants and 400 MW of batteries and sells to NIPSCO; 15 years; ~$1.4B bill credits to other customersIndiana order June 2026. See AWS Project Rainier
Entergy MississippiTraceview gas plant, 754 MWAWS prepaid equipment, transmission and substationsUnder construction, 2029
Xcel Energy2 GW contracted; Google ~1 GW in MinnesotaLarge-load tariffs with long contracts, exit fees and credit requirements in four statesGoogle deal pending
Texas SB 6 and PUCT rule75 MW and above$100,000 study fee; $50,000 per MW security; emergency curtailment of large loadsAdopted September 2026; data center permits paused by the governor
PJMNew loads 50 MW and upBackstop procurement; bring-your-own generation; curtailable connect-and-manage optionBeing implemented

National picture

Data Centers Are Most New US Load

  • Load growth: Grid Strategies forecasts 166 GW of summer peak growth from 2025 to 2030, about 90 GW of it from data centers.
  • Queues: ERCOT had more than 233 GW of large-load requests at the end of 2025, over 70% data centers; AEP Ohio alone has more than 30 GW of inquiries. See Scaling Data Center Energy.
  • FERC: in June 2026 FERC ordered six grid operators to justify or reform their rules for loads of 50 MW and up above 69 kV, covering cost shifting, flexible service and generation sited near the load.

Record

Dataset Record

Dataset
Utility-built generation and large-load tariffs for data centers
Sources
Louisiana PSC, Ohio PUCO, Virginia SCC, Georgia PSC, Wisconsin PSC, Indiana URC, PUCT, PJM, FERC, Entergy, Louisiana Illuminator, S&P Global, DatacenterDynamics, Utility Dive, POWER
Last verified
October 2026