PUE
PUE Has Stalled Industry-Wide but Not at Scale
- Industry: the Uptime Institute's 2026 survey puts the average at 1.52, barely changed since 2019 (1.54 in 2025). Weighted by facility size it is 1.36, and new large facilities routinely report 1.3 or lower.
- Hyperscalers: Google 1.09 (2025) and AWS 1.15 (2024); Microsoft's and Meta's current fleet figures were not found in their latest reports.
- Best case: NREL's ESIF in Colorado runs at 1.036 on warm-water liquid cooling and heats its own building. See Heat Reuse.
- Caps: Germany requires 1.2 or lower for new data centers from July 2026, 1.5 for existing sites by July 2027 and 1.3 by 2030, and 100% renewable electricity from 2027.
PUE measures overhead, not total energy: a campus can hit 1.1 while its total draw grows tenfold. See Scaling Data Center Energy.
Carbon
Hyperscaler Emissions Are Rising With AI
- Google: data center electricity rose about 37% in 2025 to about 42 TWh; Scope 1 and 2 emissions fell 2% while supply-chain emissions rose 25%; hourly carbon-free share slipped to 65%. Its 2030 goal of 24/7 carbon-free power stands.
- Microsoft: emissions rose from about 13 Mt CO2e in 2020 to about 20 Mt in 2025, roughly 50%, and Microsoft paused buying unbundled renewable certificates; its carbon-negative-by-2030 goal is unchanged. New designs since August 2024 use no evaporative water for cooling, with a nominal energy penalty.
- Meta: 100% of electricity matched with clean energy since 2020; location-based emissions rose in 2024.
Reporting rules
Ratings and Disclosure Arrive in 2027
- EU: the Commission adopted a mandatory A-to-G rating for data centers of 500 kW and up in September 2026, grading PUE, water use, energy sourcing, grid flexibility and heat-reuse readiness; first labels in 2027 and minimum standards proposed for mid-2027.
- California: AB 1577 (September 2026) requires operators to report location, size, PUE and onsite generator fuel to the state energy commission.
- New Jersey: a 2026 law requires data centers to disclose energy and water use every six months.
Record
Dataset Record
- Dataset
- PUE, carbon and water metrics for data centers and hyperscalers
- Sources
- Uptime Institute, Google, Microsoft, Meta, Amazon, NREL, EU Commission, California and New Jersey legislation, White & Case, Linklaters, DatacenterDynamics, The Register, S&P Global
- Last verified
- October 2026