The US sites
Seven US Campuses, About 8.5 GW Committed, One Running
Each Stargate campus is built and owned by a developer, leased by Oracle or SoftBank, and used by OpenAI.
- Leased by Oracle
- SoftBank-owned
| Site | Builder and owner | Lessee | Committed MW | Live | Energy | Status |
|---|---|---|---|---|---|---|
| Stargate Abilene, Campus 1Abilene, TX | Crusoe on Lancium land | Oracle | 1,200 | About 421 MW of IT | Grid plus onsite gas | Operating; expansion dropped March 2026 |
| Stargate Doña Ana (Project Jupiter)Santa Teresa, NM | STACK Infrastructure (Blue Owl) | Oracle | 2,200 | 0 | Behind-the-meter gas fuel cells | Under construction; permit case stayed, force majeure notice reported September 2026 |
| Vantage FrontierShackelford County, TX | Vantage Data Centers | Oracle | 1,400 | 0 | Behind-the-meter gas | Under construction; first building projected August 2027 |
| Stargate Saline TownshipSaline Township, MI | Related Digital | Oracle | 1,400 | 0 | Grid, DTE, plus batteries | Under construction; $16.3B financing |
| Stargate Port Washington (Lighthouse)Port Washington, WI | Vantage Data Centers | Oracle | 902 | 0 | Grid, We Energies | Under construction; completion 2028 |
| Stargate Milam CountyMilam County, TX | SB Energy (SoftBank) | OpenAI lease | 1,200 | 0 | Solar plus grid, reported | Under construction |
| Stargate LordstownLordstown, OH | SoftBank | OpenAI | 214 | 0 | Grid | Under construction; projected early 2027; OpenAI implies about 300 MW |
Committed figures follow the Largest Data Centers in the US ranking, where every site but Lordstown appears; Epoch AI projects lower IT figures for some, such as about 1,750 MW at Doña Ana and 857 MW at Milam. OpenAI's 3.2 GW Project Camellia in Georgia is not named as a Stargate site in its announcement and is listed separately in that ranking.
From joint venture to umbrella
Stargate Became OpenAI's Name for Leased Capacity
- January 2025: Stargate launches as a $500B, 10 GW joint venture of OpenAI, SoftBank, Oracle and MGX, chaired by SoftBank's Masayoshi Son, with Abilene as its first site.
- September 2025: Planned capacity reaches nearly 7 GW and more than $400B across five new US sites.
- February 2026: OpenAI cuts its compute spending plan to about $600B over four years, from $1.4T.
- March 2026: OpenAI and Oracle drop the Abilene expansion, which goes to Microsoft through Crusoe; OpenAI reorganizes its Stargate teams under Sachin Katti.
- April 2026: The Financial Times reports OpenAI has effectively abandoned the joint venture for bilateral leases; OpenAI calls Stargate an umbrella for its compute strategy and says it has secured more than 10 GW in the US, counting cloud capacity.
- July 2026: OpenAI announces Project Camellia, a 3.2 GW campus in Georgia; the announcement does not call it a Stargate site, though OpenAI files it under Stargate.
Who carries the debt
Oracle and Its Partners Finance Most of Stargate
- Oracle's contract: about $300B over five years for 4.5 GW, with OpenAI's payments starting in 2027.
- Oracle's balance sheet: S&P cut Oracle to BBB- in July 2026, citing its dependence on OpenAI, with debt near $167B and capital spending guidance of $90-95B for fiscal 2027.
- Partner debt: at least $72B across the Stargate sites. Saline Township's $16.3B financing closed with PIMCO anchoring about $10B after US banks pulled back.
- Project risk: Bloomberg reported in September 2026 that Oracle sent a force majeure notice on Project Jupiter to its developer, STACK Infrastructure (owned by Blue Owl), after New Mexico's Supreme Court stayed the air permit case for its fuel-cell plant. Oracle says the project remains on schedule.
Outside the US
Abu Dhabi Is the Largest Stargate Site Abroad
| Site | Location | Partners | Status |
|---|---|---|---|
| Stargate UAE | Abu Dhabi | G42 and Khazna, with Oracle | 1 GW cluster in a 5 GW campus; two 100 MW buildings enclosed, none confirmed online; being redrawn into dispersed sites |
| Stargate Norway | Narvik | Nscale and Aker | Microsoft took over the lease in April 2026, 230 MW with 30,000 Rubin GPUs; OpenAI is to lease compute from Microsoft there, the FT reports |
| Stargate UK | North East England | Nscale | Paused April 9, 2026, citing energy costs and regulation |
| India | Not disclosed | TCS HyperVault | 100 MW initial, aiming for 1 GW; framed as part of Stargate |
| Japan | Sakai, Osaka | SoftBank | 150 MW rising to 250 MW at a former Sharp plant; not officially named Stargate |
| Korea | Not disclosed | Samsung SDS, SK Telecom | Delayed by design changes |
| Australia | Sydney | NextDC | Memorandum for a 612 MW campus in early planning |
| Argentina | Patagonia | Sur Energy | No construction as of October 2026 |
OpenAI's other compute
Stargate Is One Part of OpenAI's Compute
OpenAI ran about 1.9 GW of compute across all providers at the end of 2025. Most of its contracted capacity comes from clouds and chipmakers outside Stargate.
| Partner | Deal | Notes |
|---|---|---|
| Microsoft Azure | $250B of services | Microsoft gave up its right of first refusal in October 2025 |
| AWS | $38B, plus $100B over eight years for 2 GW of Trainium | The Trainium deal was signed in February 2026 |
| CoreWeave | Up to $22.4B | Three contracts |
| Cerebras | More than $10B for 750 MW | Through 2028 |
| AMD | 6 GW of MI450 accelerators | With warrants for up to 160 million AMD shares |
| Broadcom | 10 GW of custom accelerators | From late 2026 to 2029 |
| Nvidia | $30B equity investment | Replaced a $100B, 10 GW letter of intent in February 2026 |
| Google Cloud | Size not disclosed |
The stack inside
Abilene Runs Nvidia GB200 Racks on Oracle Cloud
| Layer | At Abilene | More |
|---|---|---|
| Chips | Nvidia Blackwell GPUs and Grace CPUs | Chip depth at SemiconductorX |
| Server and rack | Nvidia GB200 NVL72 racks, owned and run by Oracle Cloud Infrastructure | See the GB200 NVL72 supplier ring |
| Cooling | Closed-loop direct-to-chip liquid cooling, with air-cooled chillers | Direct-to-Chip Cooling |
| Power | Lancium substations on the grid plus onsite gas turbines | The Abilene supplier ring on AustinIO |
Record
Dataset Record
- Dataset
- Stargate sites; US rows also in us_ai_campuses.csv
- Sources
- OpenAI, Oracle, Epoch AI, Financial Times via Tom's Hardware, DatacenterDynamics, The Next Web, Measured AI, Capacity Global, TechCrunch, CNBC, Wikipedia
- Last verified
- October 2026