Hydrogen and Fuel Cells

Fuel cells and hydrogen · Fast onsite power on natural gas; hydrogen still on paper · Flagships: Bloom Energy and Data City

Fuel cells have become the fastest way to put power on an AI campus, measured in months while new turbines take years. Bloom's deals now run to gigawatts with Oracle, AEP and Brookfield, all on natural gas; Data City's hydrogen-powered campus near Laredo has not been built.

Time to onsite power compared: Bloom fuel cells in 55 days at an Oracle site and three to 12 months typically, reciprocating engines in 24 to 36 months, and new gas turbines three to five years; and Bloom's largest data center deals TIME FROM ORDER TO POWER, MONTHS LOG SCALE 1 3 12 36 72 Bloom at Oracle (actual) Fuel cells, typical Recip engines New gas turbines BLOOM'S LARGEST DATA CENTER DEALS, MW Oracle master agreement 2,800; 1,200 firm Project Jupiter, NM 2,450 AEP Ohio option 1,000 AEP Cheyenne for Google 702 Equinix, 19 sites 105 ALL RUN ON NATURAL GAS, NOT HYDROGEN.
Bloom at Oracle
Up to 2.8 GW
Fastest delivery
55 days
Bloom output
2 GW a year by end 2026
Data City
Phase 1 canceled
Hub
Energy

Bloom fuel cells

Fuel Cells Win on Speed, Not on Fuel

  • Technology: Bloom's solid-oxide fuel cells convert natural gas to electricity electrochemically, about 53% efficient on gas (up to 90% with heat recovery), with NOx about 92% below the turbines they replaced at Project Jupiter, Oracle says. They are hydrogen-capable, but every data center deployment found runs on gas.
  • Speed: Bloom delivered Oracle's first system in 55 days; turbines now take three to five years.
  • Scale: about 1.4 GW installed at more than 1,000 sites (October 2025); factory output doubling to 2 GW a year by end of 2026; second-quarter 2026 revenue of $1.065B, up 166%.
  • Caution: Hunterbrook reported about $20B of deals marketed against $492.6M of binding obligations in SEC filings, so headline GW figures are frameworks, not orders.
  • Cost: AEP's Cheyenne plant works out to about $5,700/kW all-in; Jupiter's switch to fuel cells was reported as costlier than turbines.

Bloom deals

Bloom's Data Center Deals

Bloom fuel cell deals at data centers
CustomerScaleStatus
OracleUp to 2.8 GW master agreement; 1.2 GW contracted and deploying into 2027First system delivered in 55 days against 90 planned; designed for 800 V dc power
Project Jupiter, Dona Ana County, NM (Oracle, BorderPlex)Up to 2.45 GW, replacing planned gas turbines (April 2026)Islanded; gas pipeline stalled; first buildings mid-2027 at the earliest. See Stargate
AEP, Ohio100 MW plus a 900 MW option, mostly exercised (~$2.65B)Ohio regulators approved units at an AWS site (6-year contract) and a Cologix site (15-year)
AEP, Cheyenne, Wyoming702 MW for a Google data center, $4B, 20 yearsConstruction from 2026; full operation by end of 2028
BrookfieldUp to $5B (October 2025), expanded to a $25B financing framework (June 2026)No sites or GW named; first site in Europe
EquinixMore than 100 MW across 19 sites in six statesAbout 75 MW operating
CoreWeaveChirisa Technology Parks, Volo, IllinoisMW not disclosed

Data City

Data City Planned to Run on Hydrogen; It Has Not Been Built

  • Developer: Energy Abundance Development Corp. of Houston, formerly Green Hydrogen International, on about 50,000 acres in Webb County near Laredo, off the ERCOT grid.
  • Plan: up to 5 GW in three phases, starting with 300 MW on gas turbines, wind, solar and batteries, switching the turbines to hydrogen from its sister project, Hydrogen City, in Duval County.
  • Status: no tenant, permit or construction record found; Cleanview lists Phase 1 as canceled, and Hydrogen City has slipped to 2028 or later.

See Data City on AustinIO.

Hydrogen projects

No AI Data Center Runs on Delivered Green Hydrogen

Hydrogen and other fuel cell data center projects
ProjectPlanStatus
Data CityWebb County, near Laredo, TXUp to 5 GW off-grid; gas, wind and solar first, hydrogen later from Hydrogen CityPhase 1 listed as canceled; no permits or tenants found
Hydrogen CityPiedras Pintas salt dome, Duval County, TX2 GW of electrolysis in the 2022 plan; salt-cavern storagePushed to 2028; listed as announced
ECL TerraSite-TX1East of Houston, TX1 GW, option to 2 GW; hydrogen made from natural gas, by pipeline; Lambda first tenant2026 status not found
MSB MatrixSulphur Springs, TX800 MW of Bloom fuel cells claimed, then geothermalPhase 1 listed as canceled
FuelCell Energy and SDCLNot statedUp to 450 MWJanuary 2026

Record

Dataset Record

Dataset
Fuel cell and hydrogen power at data centers: deals, MW and status
Sources
Bloom Energy filings and releases, Oracle, AEP, Brookfield, Equinix, Ohio PUCO, Cleanview, Hunterbrook, POWER, Utility Dive, DatacenterDynamics, Bisnow
Last verified
October 2026