Models
Nine Ways Capacity Gets Built
| Model | Building owner | IT owner | Typical term | Example |
|---|---|---|---|---|
| Self-build | Hyperscaler | Hyperscaler | Owned | Microsoft Fairwater, Wisconsin |
| Build-to-suit | Developer | Tenant | 10-20 years | Vantage Frontier, Texas, for Stargate |
| Powered shell | Developer builds shell and power | Tenant fits out | 10-15 years | QTS and Digital Realty hyperscale shells |
| Wholesale lease | Operator | Tenant | 5-10 years | Iron Mountain, Northern Virginia |
| Retail colocation | Operator | Tenant's cabinets | 1-3 years | Equinix Ashburn |
| Neocloud | Leases from developers or owns | Neocloud rents GPUs | 2-5+ years, take-or-pay | CoreWeave; Nebius, Vineland, NJ |
| Joint venture | Investor-majority venture | Hyperscaler | 4-year renewals, residual value guarantee | Meta Hyperion with Blue Owl |
| Behind the meter | Owner-operator, own power plant | Owner-operator | Owned | SpaceX Colossus 2 |
| Modular | Owner, with factory-built modules | Owner or tenant | Varies | See Modular Data Centers |
Who finances each layer, and who carries the risk, is covered in Business Models.
Cost
A Megawatt Costs About $50 Million, Chips Included
- Facility: $17.6 million per MW all-in for a new US campus in 2026, excluding chips, up 21% since late 2024; power infrastructure is about a fifth of it (Cushman & Wakefield).
- Shell: $10.5 million per MW in Dallas, Phoenix and Atlanta, $11.5 million in Northern Virginia and $13.0 million in Chicago (JLL).
- AI premium: liquid-cooled AI halls cost about 7% to 10% more (Turner & Townsend).
- All-in: Nvidia's Jensen Huang puts a 1 GW AI factory at about $50 billion and says the figure is rising toward $100 billion as grid work gets harder.
Time to power
Power, Not Construction, Sets the Schedule
- Grid: about four years on average in the US for a large connection, and about seven years for 100 MW in Northern Virginia (JLL).
- Equipment: large transformers take two to four years to arrive; the shell building takes 18 to 24 months.
- Behind the meter: SpaceX's Colossus 1 in Memphis went from empty factory to training in about four months on portable gas turbines, and Colossus 2 runs fully off the grid. About $500 million buys 350 MW of on-site turbines (iMasons). See Onsite Gas.
Neoclouds
Neoclouds Rent GPUs Under Long Contracts
- CoreWeave: $104 billion contract backlog, 1.5 GW active and 4.2 GW contracted as of Q2 2026, with $35-39 billion of 2026 capex.
- Nebius: targets 5 GW contracted by the end of 2026 and more than $40 billion of committed backlog; its US site is Vineland, New Jersey.
- Crusoe: 4.9 GW contracted, including Stargate Abilene for Oracle and a separate 900 MW Abilene campus for Microsoft.
Record
Dataset Record
- Dataset
- Deployment models, build cost per MW and time to power
- Sources
- Cushman & Wakefield 2026 Data Center Development Cost Guide, JLL 2026 Global Outlook, Turner & Townsend, iMasons, Nvidia, CoreWeave, Nebius and Crusoe disclosures, company filings
- Last verified
- October 2026