Deployment Models

How data center capacity gets built · Self-build to neocloud · Cost per megawatt and time to power

Data center capacity is built nine ways, from hyperscalers' own campuses to neoclouds renting GPUs on take-or-pay contracts. A US megawatt now costs about $17.6 million for the building alone, and about $50 million with chips; grid power, at four to seven years, sets the schedule more than construction does.

What a megawatt of AI capacity costs: about $17.6 million for the facility, excluding chips, within Nvidia's roughly $50 billion per gigawatt all-in; and how long each step takes, from about four months for Colossus 1 on portable turbines to about seven years for a 100 MW grid connection in Northern Virginia WHAT A MEGAWATT COSTS, $M (2026) Nvidia all-in~$50B per GW Facility 17.6Chips, servers, network ~32 Shell onlyJLL, by market 10.5 Dallas, Phoenix, Atlanta to 13.0 Chicago HOW LONG EACH STEP TAKES, YEARS 0 2 4 6 8 Colossus 1Portable turbines Shell buildingConcrete to roof Large transformerLead time Grid connectionUS average Grid, 100 MWNorthern Virginia
Facility
$17.6M per MW
All-in, Nvidia
~$50B per GW
Grid wait, US
~4 years
CoreWeave backlog
$104B
Hub
Types

Models

Nine Ways Capacity Gets Built

Data center deployment models
ModelBuilding ownerIT ownerTypical termExample
Self-buildHyperscalerHyperscalerOwnedMicrosoft Fairwater, Wisconsin
Build-to-suitDeveloperTenant10-20 yearsVantage Frontier, Texas, for Stargate
Powered shellDeveloper builds shell and powerTenant fits out10-15 yearsQTS and Digital Realty hyperscale shells
Wholesale leaseOperatorTenant5-10 yearsIron Mountain, Northern Virginia
Retail colocationOperatorTenant's cabinets1-3 yearsEquinix Ashburn
NeocloudLeases from developers or ownsNeocloud rents GPUs2-5+ years, take-or-payCoreWeave; Nebius, Vineland, NJ
Joint ventureInvestor-majority ventureHyperscaler4-year renewals, residual value guaranteeMeta Hyperion with Blue Owl
Behind the meterOwner-operator, own power plantOwner-operatorOwnedSpaceX Colossus 2
ModularOwner, with factory-built modulesOwner or tenantVariesSee Modular Data Centers

Who finances each layer, and who carries the risk, is covered in Business Models.

Cost

A Megawatt Costs About $50 Million, Chips Included

  • Facility: $17.6 million per MW all-in for a new US campus in 2026, excluding chips, up 21% since late 2024; power infrastructure is about a fifth of it (Cushman & Wakefield).
  • Shell: $10.5 million per MW in Dallas, Phoenix and Atlanta, $11.5 million in Northern Virginia and $13.0 million in Chicago (JLL).
  • AI premium: liquid-cooled AI halls cost about 7% to 10% more (Turner & Townsend).
  • All-in: Nvidia's Jensen Huang puts a 1 GW AI factory at about $50 billion and says the figure is rising toward $100 billion as grid work gets harder.

Time to power

Power, Not Construction, Sets the Schedule

  • Grid: about four years on average in the US for a large connection, and about seven years for 100 MW in Northern Virginia (JLL).
  • Equipment: large transformers take two to four years to arrive; the shell building takes 18 to 24 months.
  • Behind the meter: SpaceX's Colossus 1 in Memphis went from empty factory to training in about four months on portable gas turbines, and Colossus 2 runs fully off the grid. About $500 million buys 350 MW of on-site turbines (iMasons). See Onsite Gas.

Neoclouds

Neoclouds Rent GPUs Under Long Contracts

  • CoreWeave: $104 billion contract backlog, 1.5 GW active and 4.2 GW contracted as of Q2 2026, with $35-39 billion of 2026 capex.
  • Nebius: targets 5 GW contracted by the end of 2026 and more than $40 billion of committed backlog; its US site is Vineland, New Jersey.
  • Crusoe: 4.9 GW contracted, including Stargate Abilene for Oracle and a separate 900 MW Abilene campus for Microsoft.

Record

Dataset Record

Dataset
Deployment models, build cost per MW and time to power
Sources
Cushman & Wakefield 2026 Data Center Development Cost Guide, JLL 2026 Global Outlook, Turner & Townsend, iMasons, Nvidia, CoreWeave, Nebius and Crusoe disclosures, company filings
Last verified
October 2026