Nuclear power for data centers · Restarts, existing-plant contracts, uprates and new reactors · Flagship: Crane Clean Energy Center, Pennsylvania

Data center companies have contracted more than 10 GW of nuclear power, but almost none of it reaches them before 2027. Restarts like Microsoft's Crane come first, long contracts with running plants ramp through 2032, and new reactors, small or large, are 2030s supply.

When nuclear power contracted by data center companies comes online, 2026 to 2036: restarts first, then existing-plant contracts ramping up, uprates, and new reactors in the 2030s NUCLEAR FOR DATA CENTERS: WHEN IT ARRIVES MW 2026 2028 2030 2032 2034 2036 Crane restartMicrosoft · 835 MW ClintonMeta · 1,121 MW Comanche PeakAmazon, reported · 1,200 MW SusquehannaAWS · 1,920 MW Duane Arnold restartGoogle · 615 MW Palisades restartNot named · ~800 MW Kairos Hermes 2Google via TVA · 50 MW Vistra upratesMeta · 433 MW Oklo, Pike County OHMeta · 1,200 MW TerraPower NatriumMeta · ~2,800 MW Restart Existing plant Uprate New reactor OPEN: RAMPING UP. SOLID: FULL VOLUME. PALISADES HAS NO RESTART DATE.
Crane
835 MW, Microsoft
Crane restart
2027 target
Largest contract
Susquehanna, 1,920 MW
First new SMR permit
Clinch River, 2026
Federal target
400 GW by 2050
Hub
Energy

Crane restart

Microsoft Brings Three Mile Island Unit 1 Back

  • Plant: 835 MW, a single pressurized-water reactor shut in 2019, renamed the Crane Clean Energy Center.
  • Contract: a 20-year power purchase agreement with Microsoft, announced September 2024. Constellation's restart cost has been reported at about $1.6B; the Energy Department closed a $1B loan in November 2025.
  • Licensing: the NRC finished its environmental review in September 2026 and approved the fuel amendment; the main operating approvals were still pending in late September.
  • Grid: in June 2026 FERC let Constellation move 760 MW of grid connection rights from its Eddystone units to Crane, so the plant can run fully before PJM finishes upgrades that may extend past 2030.
  • Target: restart in 2027, moved up from 2028. The license runs to 2034, with an extension to 2054 planned.

Microsoft does not take the power directly: Crane sells into the PJM grid, and the contract matches Microsoft's consumption there.

Restarts

Closed Plants Are the Fastest New Nuclear

Restarting a recently closed plant takes three to five years against a decade or more for a new reactor.

Nuclear restarts
PlantMWBuyerStatus
Palisades, Michigan (Holtec)About 800Contract to supply power by March 2027; buyers not namedFuel loading paused after a fuel assembly tipped in August 2026; no restart date. Two Holtec SMR-300 units planned on site by 2031
Duane Arnold, Iowa (NextEra)615Google, 25 years$1.9B Energy Department loan (September 2026); online late 2028 to early 2029

Existing plants

Long Contracts With Running Plants

Most nuclear power for data centers comes from running plants under 20-year contracts, delivered over the grid.

Contracts with operating nuclear plants
PlantMWContractNotes
Susquehanna, Pennsylvania (Talen)Up to 1,920AWS, through 2042, $18B; 840-1,200 MW by 2029, full by 2032Moved from behind the meter to grid delivery in spring 2026. See AWS Project Rainier
Clinton, Illinois (Constellation)1,121Meta, 20 years from June 2027Includes a 30 MW uprate
Comanche Peak, Texas (Vistra)1,20020 years from late 2027; buyer reported as AmazonFull volume by 2032
Perry, Davis-Besse, Beaver Valley (Vistra)433Meta, uprates, early 2030sSigned January 2026

New reactors

New Reactors Arrive in the 2030s

New reactors tied to data center buyers
ProjectMWBuyer or designStatus
Clinch River, Tennessee (TVA)300GE Vernova Hitachi BWRX-300First US construction permit for the design, September 2026, after 14 months
Hermes 2, Oak Ridge (Kairos)50Google through TVA; part of a 500 MW fleet dealGround broken April 2026; operation by 2030
Pike County, Ohio (Oklo)Up to 1,200MetaFirst power as early as 2030; full by 2034
Natrium (TerraPower)About 2,800 plus storageMeta: two units funded, rights to six moreBy 2035
Xe-100, Washington (X-energy, Energy Northwest)320, up to 960Amazon, options on 5 GW by 2039No construction permit filed; X-energy listed April 2026
Fermi America, AmarilloAbout 4,400 (four AP1000s)Fermi AmericaDraft environmental review done; no safety-review date. See Fermi America Matador
Westinghouse AP1000 program$80B of buildsUS government, October 2025Sites and count not specified; construction from about 2030

Google also funds early work on three Elementl sites of at least 600 MW each, and Amazon has a 2024 agreement with Dominion to explore a small reactor at North Anna, Virginia; neither has a 2026 milestone.

Co-location rules

FERC Pushed Co-Location Back Onto the Grid

  • Susquehanna: FERC rejected an agreement in November 2024 that would have let the AWS campus take more power directly from the plant, behind the meter. Talen and AWS moved to grid delivery instead.
  • PJM order: in December 2025 FERC found PJM's rules unjust and ordered three new transmission services for co-located load, including an interim non-firm option, with limits on netting load behind the meter. PJM filed compliance in early 2026; a final ruling has not been reported.
  • Federal policy: May 2025 executive orders target 400 GW of US nuclear by 2050, 10 large reactors under construction by 2030 and 18-month NRC decisions. The NRC published its Part 53 rule for advanced reactors in March 2026 and set a November 2026 deadline for its rule rewrite.

Record

Dataset Record

Dataset
Nuclear supply contracted by data center companies: plant, MW, buyer, date and status
Sources
NRC, FERC, Federal Register, Energy Department Loan Programs Office, Constellation, Talen, Vistra, NextEra, Holtec, TVA, Oklo, X-energy, World Nuclear News, American Nuclear Society, Utility Dive, POWER