Crane restart
Microsoft Brings Three Mile Island Unit 1 Back
- Plant: 835 MW, a single pressurized-water reactor shut in 2019, renamed the Crane Clean Energy Center.
- Contract: a 20-year power purchase agreement with Microsoft, announced September 2024. Constellation's restart cost has been reported at about $1.6B; the Energy Department closed a $1B loan in November 2025.
- Licensing: the NRC finished its environmental review in September 2026 and approved the fuel amendment; the main operating approvals were still pending in late September.
- Grid: in June 2026 FERC let Constellation move 760 MW of grid connection rights from its Eddystone units to Crane, so the plant can run fully before PJM finishes upgrades that may extend past 2030.
- Target: restart in 2027, moved up from 2028. The license runs to 2034, with an extension to 2054 planned.
Microsoft does not take the power directly: Crane sells into the PJM grid, and the contract matches Microsoft's consumption there.
Restarts
Closed Plants Are the Fastest New Nuclear
Restarting a recently closed plant takes three to five years against a decade or more for a new reactor.
| Plant | MW | Buyer | Status |
|---|---|---|---|
| Palisades, Michigan (Holtec) | About 800 | Contract to supply power by March 2027; buyers not named | Fuel loading paused after a fuel assembly tipped in August 2026; no restart date. Two Holtec SMR-300 units planned on site by 2031 |
| Duane Arnold, Iowa (NextEra) | 615 | Google, 25 years | $1.9B Energy Department loan (September 2026); online late 2028 to early 2029 |
Existing plants
Long Contracts With Running Plants
Most nuclear power for data centers comes from running plants under 20-year contracts, delivered over the grid.
| Plant | MW | Contract | Notes |
|---|---|---|---|
| Susquehanna, Pennsylvania (Talen) | Up to 1,920 | AWS, through 2042, $18B; 840-1,200 MW by 2029, full by 2032 | Moved from behind the meter to grid delivery in spring 2026. See AWS Project Rainier |
| Clinton, Illinois (Constellation) | 1,121 | Meta, 20 years from June 2027 | Includes a 30 MW uprate |
| Comanche Peak, Texas (Vistra) | 1,200 | 20 years from late 2027; buyer reported as Amazon | Full volume by 2032 |
| Perry, Davis-Besse, Beaver Valley (Vistra) | 433 | Meta, uprates, early 2030s | Signed January 2026 |
New reactors
New Reactors Arrive in the 2030s
| Project | MW | Buyer or design | Status |
|---|---|---|---|
| Clinch River, Tennessee (TVA) | 300 | GE Vernova Hitachi BWRX-300 | First US construction permit for the design, September 2026, after 14 months |
| Hermes 2, Oak Ridge (Kairos) | 50 | Google through TVA; part of a 500 MW fleet deal | Ground broken April 2026; operation by 2030 |
| Pike County, Ohio (Oklo) | Up to 1,200 | Meta | First power as early as 2030; full by 2034 |
| Natrium (TerraPower) | About 2,800 plus storage | Meta: two units funded, rights to six more | By 2035 |
| Xe-100, Washington (X-energy, Energy Northwest) | 320, up to 960 | Amazon, options on 5 GW by 2039 | No construction permit filed; X-energy listed April 2026 |
| Fermi America, Amarillo | About 4,400 (four AP1000s) | Fermi America | Draft environmental review done; no safety-review date. See Fermi America Matador |
| Westinghouse AP1000 program | $80B of builds | US government, October 2025 | Sites and count not specified; construction from about 2030 |
Google also funds early work on three Elementl sites of at least 600 MW each, and Amazon has a 2024 agreement with Dominion to explore a small reactor at North Anna, Virginia; neither has a 2026 milestone.
Co-location rules
FERC Pushed Co-Location Back Onto the Grid
- Susquehanna: FERC rejected an agreement in November 2024 that would have let the AWS campus take more power directly from the plant, behind the meter. Talen and AWS moved to grid delivery instead.
- PJM order: in December 2025 FERC found PJM's rules unjust and ordered three new transmission services for co-located load, including an interim non-firm option, with limits on netting load behind the meter. PJM filed compliance in early 2026; a final ruling has not been reported.
- Federal policy: May 2025 executive orders target 400 GW of US nuclear by 2050, 10 large reactors under construction by 2030 and 18-month NRC decisions. The NRC published its Part 53 rule for advanced reactors in March 2026 and set a November 2026 deadline for its rule rewrite.
Record
Dataset Record
- Dataset
- Nuclear supply contracted by data center companies: plant, MW, buyer, date and status
- Sources
- NRC, FERC, Federal Register, Energy Department Loan Programs Office, Constellation, Talen, Vistra, NextEra, Holtec, TVA, Oklo, X-energy, World Nuclear News, American Nuclear Society, Utility Dive, POWER
- Last verified
- October 2026