Battery Storage

Battery storage at AI campuses · Ride-through, smoothing and grid support · Flagship: Colossus Megapacks, Memphis

AI training makes a campus's power draw swing by hundreds of megawatts in step, and utilities now ask large loads to drop off the grid on call. At Colossus 2 in Memphis, SpaceXSI has assembled roughly 2.8 to 3.3 GWh of Tesla Megapacks, about the size of the largest grid battery in the US.

Illustration of an AI training load swinging by hundreds of megawatts as GPUs alternate between compute and communication, and the smoother grid draw when a battery absorbs the swings, with the Colossus 2 battery figures WHY TRAINING CAMPUSES ADD BATTERIES ILLUSTRATIVE GPU LOAD Compute phaseCommunication phase GRID DRAW WITH BATTERY Smoothed Load can change by up to 50% within minutes, Fluence says; NERC linksseveral 1 GW+ sudden data center load losses in 2024-2025 to grid risk. COLOSSUS 2 BATTERY, MEMPHIS ~720Megapack containers counted, July 2026 2.8-3.3 GWhcounted vs. claimed by SpaceXSI ~2,000 MWbehind the meter, MLGW CEO 4 hoursoff-grid on MLGW's call For comparison, the largest US grid battery, Edwards and Sanborn, is about 3.3 GWh.
Colossus 2 battery
2.8-3.3 GWh
Containers
About 720
Off-grid on call
4 hours
Megapack spend
$835M, 2025-H1 2026
Hub
Energy

Colossus Megapacks

A Grid-Scale Battery Behind One Data Center

  • Colossus 1: Tesla Megapacks were installed in 2025; reported counts of 168 and 119 (about 120 MW) do not reconcile.
  • Colossus 2: satellite imagery in July 2026 showed about 720 Megapack containers, about 2.8 GWh by Canary Media's count; SpaceXSI told the TVA board 3.3 GWh, and MLGW's CEO described about 2,000 MW behind the meter.
  • Confirmed role: the battery is a condition of service under MLGW's power-interruption program, letting the site leave the grid for four hours to shed load. Smoothing training swings is likely but unconfirmed; selling peak capacity to TVA is possible, with no contract announced.
  • Spend: SpaceXSI bought $430M of Megapacks in 2025 and $405M more in the first half of 2026, per Tesla filings.

See SpaceX Colossus and Onsite Gas.

Load swings

Training Loads Swing Together

  • The problem: thousands of GPUs alternate between computing and exchanging results in step, so a campus's draw swings by hundreds of megawatts.
  • Rack level: Nvidia's GB300 NVL72 stores about 65 joules per GPU in power-supply capacitors, ramps power gradually at job start and burns power during lulls to taper ramp-downs; Nvidia reports 30% lower peak grid demand on one training job. It does not replace a site battery.
  • Grid operators: NERC issued a Level 3 alert in 2026 requiring utilities to plan for data center load behavior, after several incidents in 2024 and 2025 where more than 1 GW of data center load dropped at once.
  • UPS versus battery storage: a UPS bridges seconds to minutes per hall until generators start; site battery storage, sized in MW and MWh, smooths load, shaves peaks, stabilizes islanded grids and can black-start them.

Sizing

Sizing Batteries for a Grid-Tied Training Campus

A grid-tied campus still needs storage at four timescales, because each layer covers a gap the next one is too slow or too small to fill. The figures below are for a 1 GW training campus.

Storage layers for a 1 GW grid-tied training campus
LayerCoversDurationSizing at 1 GW
Rack power-supply capacitorsSub-cycle dips and the first moments of a faultAbout 20 msBuilt into each rack; Nvidia's GB300 NVL72 stores about 65 joules per GPU
Supercapacitors and rack battery unitsFast training swings, generator handoffSeconds; Open Compute's Mt Diablo spec offers 45-90 sRated for power, not energy
UPS batteriesOutage until generators startAbout 5-10 minutesAbout 100 MWh (E Source); current designs carry at least 20% redundancy
Site battery storageSmoothing training swings, peak shaving, curtailment on callAbout 1-2 hoursAbout 0.7-1 GW of power and 0.7-2 GWh of energy (panel estimate)
  • Power, not just energy: smoothing calls for batteries that charge and discharge fast. Siemens Energy rates its BlueVault system at about 2C charge and 4C discharge, against about 0.5C for typical grid storage.
  • Rule of thumb: on a March 2026 Energy Storage Summit panel, a BrightNight executive put smoothing batteries at about 70-100% of the data center's power demand with one to two hours of duration. That is a panel estimate, not a published standard.
  • Check against Colossus 2: about 2.8-3.3 GWh behind about 2 GW of load is roughly 1.4-1.6 hours at full draw, inside that range.
  • The rule driving it: ERCOT has proposed limiting large loads to 10 MW of swing in any 5 seconds, about 2 MW per second. A campus whose training jobs swing by hundreds of megawatts cannot meet that without storage or rack-level power smoothing.
  • Grid-tied is not grid-only: utilities increasingly require large loads to leave the grid on call, as MLGW does in Memphis, which needs hours of storage or onsite generation.

The power chain from substation to chip is on Power Distribution.

Other campus batteries

Batteries at Other AI Campuses

Battery storage at AI campuses
ProjectBatteryStatus
Intersect and Google QuantumHaskell County, TX640 MW solar plus 1.3 GWhOperating since June 2026
GW RanchPecos County, TX1.8 GW, MWh not disclosedPlanned by 2031
PaducahPaducah, KYUp to 2.6 GW, built by NextEra, with 2 GW of gasComplete in 2032
Google and Xcel, Form Energy iron-airPine Island, MN300 MW / 30 GWh, 100-hour durationAnnounced February 2026
Crusoe and Form EnergySite not stated12 GWh iron-airAnnounced March 2026
Crusoe and Redwood MaterialsSparks, NVSecond-life EV batteries plus solar; about 20 MW of modular data centersOperating
Joule Capital PartnersMillard County, UT1.1 GWh grid-formingOff-grid campus
Crusoe Abilene expansionAbilene, TXMedium-voltage battery, size not disclosed2027

Fluence signed master supply agreements with two unnamed hyperscalers in May 2026 and booked about $850M of data center orders through July.

Record

Dataset Record

Dataset
Battery storage at AI campuses: MW, MWh, role and status
Sources
Tesla filings, MLGW, TVA, Canary Media, Cleanview, NERC, Nvidia, Fluence, E Source, Open Compute Project, Siemens Energy, Energy Storage Summit USA, ERCOT, POWER, ESS News, pv magazine, Rigzone, DatacenterDynamics
Last verified
October 2026