Colossus Megapacks
A Grid-Scale Battery Behind One Data Center
- Colossus 1: Tesla Megapacks were installed in 2025; reported counts of 168 and 119 (about 120 MW) do not reconcile.
- Colossus 2: satellite imagery in July 2026 showed about 720 Megapack containers, about 2.8 GWh by Canary Media's count; SpaceXSI told the TVA board 3.3 GWh, and MLGW's CEO described about 2,000 MW behind the meter.
- Confirmed role: the battery is a condition of service under MLGW's power-interruption program, letting the site leave the grid for four hours to shed load. Smoothing training swings is likely but unconfirmed; selling peak capacity to TVA is possible, with no contract announced.
- Spend: SpaceXSI bought $430M of Megapacks in 2025 and $405M more in the first half of 2026, per Tesla filings.
See SpaceX Colossus and Onsite Gas.
Load swings
Training Loads Swing Together
- The problem: thousands of GPUs alternate between computing and exchanging results in step, so a campus's draw swings by hundreds of megawatts.
- Rack level: Nvidia's GB300 NVL72 stores about 65 joules per GPU in power-supply capacitors, ramps power gradually at job start and burns power during lulls to taper ramp-downs; Nvidia reports 30% lower peak grid demand on one training job. It does not replace a site battery.
- Grid operators: NERC issued a Level 3 alert in 2026 requiring utilities to plan for data center load behavior, after several incidents in 2024 and 2025 where more than 1 GW of data center load dropped at once.
- UPS versus battery storage: a UPS bridges seconds to minutes per hall until generators start; site battery storage, sized in MW and MWh, smooths load, shaves peaks, stabilizes islanded grids and can black-start them.
Sizing
Sizing Batteries for a Grid-Tied Training Campus
A grid-tied campus still needs storage at four timescales, because each layer covers a gap the next one is too slow or too small to fill. The figures below are for a 1 GW training campus.
| Layer | Covers | Duration | Sizing at 1 GW |
|---|---|---|---|
| Rack power-supply capacitors | Sub-cycle dips and the first moments of a fault | About 20 ms | Built into each rack; Nvidia's GB300 NVL72 stores about 65 joules per GPU |
| Supercapacitors and rack battery units | Fast training swings, generator handoff | Seconds; Open Compute's Mt Diablo spec offers 45-90 s | Rated for power, not energy |
| UPS batteries | Outage until generators start | About 5-10 minutes | About 100 MWh (E Source); current designs carry at least 20% redundancy |
| Site battery storage | Smoothing training swings, peak shaving, curtailment on call | About 1-2 hours | About 0.7-1 GW of power and 0.7-2 GWh of energy (panel estimate) |
- Power, not just energy: smoothing calls for batteries that charge and discharge fast. Siemens Energy rates its BlueVault system at about 2C charge and 4C discharge, against about 0.5C for typical grid storage.
- Rule of thumb: on a March 2026 Energy Storage Summit panel, a BrightNight executive put smoothing batteries at about 70-100% of the data center's power demand with one to two hours of duration. That is a panel estimate, not a published standard.
- Check against Colossus 2: about 2.8-3.3 GWh behind about 2 GW of load is roughly 1.4-1.6 hours at full draw, inside that range.
- The rule driving it: ERCOT has proposed limiting large loads to 10 MW of swing in any 5 seconds, about 2 MW per second. A campus whose training jobs swing by hundreds of megawatts cannot meet that without storage or rack-level power smoothing.
- Grid-tied is not grid-only: utilities increasingly require large loads to leave the grid on call, as MLGW does in Memphis, which needs hours of storage or onsite generation.
The power chain from substation to chip is on Power Distribution.
Other campus batteries
Batteries at Other AI Campuses
| Project | Battery | Status |
|---|---|---|
| Intersect and Google QuantumHaskell County, TX | 640 MW solar plus 1.3 GWh | Operating since June 2026 |
| GW RanchPecos County, TX | 1.8 GW, MWh not disclosed | Planned by 2031 |
| PaducahPaducah, KY | Up to 2.6 GW, built by NextEra, with 2 GW of gas | Complete in 2032 |
| Google and Xcel, Form Energy iron-airPine Island, MN | 300 MW / 30 GWh, 100-hour duration | Announced February 2026 |
| Crusoe and Form EnergySite not stated | 12 GWh iron-air | Announced March 2026 |
| Crusoe and Redwood MaterialsSparks, NV | Second-life EV batteries plus solar; about 20 MW of modular data centers | Operating |
| Joule Capital PartnersMillard County, UT | 1.1 GWh grid-forming | Off-grid campus |
| Crusoe Abilene expansionAbilene, TX | Medium-voltage battery, size not disclosed | 2027 |
Fluence signed master supply agreements with two unnamed hyperscalers in May 2026 and booked about $850M of data center orders through July.
Record
Dataset Record
- Dataset
- Battery storage at AI campuses: MW, MWh, role and status
- Sources
- Tesla filings, MLGW, TVA, Canary Media, Cleanview, NERC, Nvidia, Fluence, E Source, Open Compute Project, Siemens Energy, Energy Storage Summit USA, ERCOT, POWER, ESS News, pv magazine, Rigzone, DatacenterDynamics
- Last verified
- October 2026