Facility Layer

The building around the racks · Shell, floors, fire and security · Flagship: Microsoft Fairwater Wisconsin

AI turned the data hall inside out: support gear now takes more floor than the racks. In a 2026 AI pod, 9 m of racks need about 16 m of electrical and mechanical plant, racks weigh up to 4,000 lb, and Microsoft's Fairwater stacks racks on two stories to shorten cables.

How AI changed the data hall: in a legacy pod about 15 meters of racks share 2 to 3 meters of support space, while in a 2026 AI pod 9 meters of racks need 9.6 meters of electrical gear and 6 to 7 meters of mechanical plant; and what went into Microsoft Fairwater Wisconsin: 46.6 miles of foundation piles, 26.5 million pounds of steel, 120 miles of underground cable and 72.6 miles of piping DEPTH OF ONE POD, METERS: RACKS vs. SUPPORT GEAR 0 5 10 15 20 25 Legacy pod Racks 15 AI pod, 2026 Racks 9 Electrical 9.6 Mech. 6.5 WHAT WENT INTO FAIRWATER WISCONSIN 46.6 milesof foundation piles 26.5M lbof structural steel 120 milesof underground cable 72.6 milesof mechanical piping Racks on two stories to shorten cables; over 90% of load liquid cooled.
Cost per MW, pre-chips
$8.9-23.3M
Rack weight
3,300-4,000 lb
Fairwater WI
1.2M sq ft
Colossus 1 build
122 days
Hub
Stack

What it is

The Building Around the Racks

The facility layer is the building: its shell, floors, power and cooling rooms, fire protection and security. AI has changed it more than anything since raised floors.

  • Support gear grows: in one measured 2026 AI hall, each pod held 9 m of racks against 9.6 m of electrical gear and 6-7 m of mechanical plant. A legacy pod had about 15 m of racks and 2-3 m of support space.
  • Heavier racks: AI racks weigh 3,300-4,000 lb, so most AI halls sit on reinforced slab floors.
  • Cost: a new US building costs $8.9 million to $23.3 million per MW before chips, up 21% since late 2024 (Cushman & Wakefield).
  • Speed: leading builders target one to two years from groundbreaking to 1 GW; SpaceXSI's Colossus 1 went live in 122 days inside a reused Memphis factory.

Flagship

Microsoft Fairwater Wisconsin: Racks on Two Stories

  • Layout: three buildings totaling 1.2 million sq ft on 315 acres in Mount Pleasant, Wisconsin, with racks laid out across two stories so cables between GPUs run shorter.
  • Materials: 46.6 miles of foundation piles, 26.5 million lb of structural steel, 120 miles of underground cable and 72.6 miles of mechanical piping.
  • Cooling: closed-loop liquid cooling for more than 90% of the load, served by what Microsoft calls the world's second-largest water-cooled chiller plant.
  • Status: Building 1 went live in April 2026 at about 369 MW of IT load. See Microsoft Fairwater.

Fire and safety

Lithium-Ion Batteries Are the New Fire Risk

  • Layers: aspirating smoke detection, pre-action sprinklers and clean-agent gas, under NFPA 75 and 76. FM-200 is being phased down under the AIM Act through 2036.
  • Batteries: no agent stops a lithium-ion thermal runaway once it starts, so battery rooms are two-hour fire rated with cell-level monitoring and automatic disconnects.
  • Daejeon, 2025: a UPS battery fire at South Korea's National Information Resources Service destroyed 384 batteries, took about 22 hours to control and took down 96 government services.

Systems

Facility Systems

Facility systems
SystemWhatNotes
Building shellSingle-story slab on grade is standard; Microsoft Fairwater stacks racks on two storiesStargate Abilene, Project Rainier; Fairwater Wisconsin and Atlanta
FloorsGB300 and Rubin racks weigh 3,300-4,000 lb, beyond typical raised-floor ratingsReinforced slab pads
Gray spaceElectrical gear now takes more pod depth than racks in AI hallsSidecar power racks move conversion out of IT racks
Fire detectionAspirating smoke detection (VESDA), pre-action sprinklersNFPA 75, 76, 72
Fire suppressionClean agents FK-5-1-12 or inert gas; FM-200 phased down through 2036Lithium-ion battery rooms: two-hour rated, cell monitoring, NFPA 855
Physical securityFences, vehicle barriers, guarded gates, mantraps, biometrics, CCTVLayered from perimeter to cage
Building managementBMS and EPMS tie power, cooling, coolant units and leak detection togetherSee Software Stack

Record

Dataset Record

Dataset
Data center buildings: shells, floors, support space, fire protection and costs
Sources
Microsoft, Cushman & Wakefield, w.media, Introl, Epoch AI, NFPA, fireprotectionfinder, DatacenterDynamics
Last verified
October 2026